Daniel Wood
Partner
Article
13
In the recent case of C Spencer Limited v MW High Tech Projects UK Limited [2019], the Technology and Construction Court (TCC) was required to consider whether, for the purposes of s.111 of the Housing Grants, Construction and Regeneration Act 1996 (as amended) (the "Act"), a valid payment notice is required to identify separately the sums due and the basis of the calculation of those sums for construction and non-construction operations.
We previously outlined what constitutes construction operations in our insight 'Are my works construction operations?'.
MW High Tech Projects UK Limited ("MW") had engaged C Spencer Limited ("CSL") under a sub-contract (in the IChemE Form of Contract for Civil Engineering Subcontracts (the Brown Book) 3rd edition 2013 with amendments) to design and construct the civil, structural and architectural works for the completion of a power plant (the "Sub-Contract"). The Sub-Contract works included construction operations for the purposes of s.105 (1) of the Act and the assembly of plant and erection of steelwork to provide support of access to plant and machinery, which are deemed as non-construction operations for the purposes of s.105 (2) of the Act. The Sub-Contract provided for periodic interim payments.
In 2018, CSL submitted Interim Payment Application number 31. Both Interim Payment Application 31 and the payment certificate issued by MW did not separate out the sums due for the construction operations and the sums due for the non-construction operations. A dispute arose between the parties over Interim Payment Application 31 and in July 2018 CSL issued a notice of intention to refer the dispute to adjudication. MW challenged the adjudicator's jurisdiction, on the grounds that the adjudication provision in the Sub-Contract was limited to disputes in respect of construction operations within the Act. The adjudicator lacked jurisdiction because the dispute as framed did not distinguish between construction operations and non-construction operations, for the purposes of the Act, and the associated sums. CSL subsequently withdrew its adjudication claim as a result of the jurisdictional challenge.
On 4 February 2019, CSL issued Interim Payment Application 32 for £3,353,219.22 plus VAT, of which £2,683,617.09 plus VAT was claimed for construction operations. Interim Payment Application 32 included a breakdown of the sum claimed which distinguished between the construction and non-construction operations. In its covering letter, CSL stated that as the Sub-Contract is a hybrid contract, Interim Payment Application 32 draws a distinction between construction and non-construction operations and welcomed a payment certificate setting out separately the sums due in respect of the construction and non-construction operations. On 19 February 2019, MW issued Payment Notice 35 stating that, in respect of Interim Payment Application 32, it considered CSL owed it £6, 818, 521.70 excluding VAT. MW also attached a spreadsheet setting out a breakdown of the measured work and variations, which indicated a negative sum due to CSL. Both Payment Notice 35 and the breakdown did not distinguish between construction and non-construction operations.
CSL's solicitors wrote to MW claiming £2,683,617.09 plus VAT as the notified sum due in the absence of any valid payment notice or pay less notice. MW's solicitor's responded arguing that MW's failure to specify the sums due for construction operations and the sums due for non-construction operations did not invalidate MW's payment notice.
CSL subsequently commenced Part 8 proceedings seeking payment of £2,683,617.09 plus VAT and/or damages in the same sum and interest. CSL argued that the proper construction of the Act and clause 38.4 of the Sub-Contract required payment notices to separately identify the sums due for construction operations and the basis on which that sum is calculated; Payment Notice 35 was not a valid payment notice for the purposes of s.110A(2) of the Act because it failed to separately identify the sums due for construction operations and the basis on which that sum is calculated; and in the absence of a valid payment notice or pay less notice, pursuant to s.111 of the Act, the notified sum to which CSL was entitled was the amount assessed in Interim Payment Application 32. MW argued, amongst other things, that the payment provisions in the Sub-Contract were compliant with the Act; Payment Notice 36 complied with the requirements in s.110A of the Act; and that the parties had decided that construction and non-construction operations would be subject to the same payment regime.
The Court held that where, as in this case, a contract contains a payment mechanism that complies with the relevant provisions of the Act and applies to both construction and non-construction operations, a payment notice that does not separate the sums due and the basis of the calculation of that sum for construction operations is valid for the purposes of s.110A and s.111 of the Act. The Court reasoned that:
The Court also held that CSL was required to identify the sums claimed for the construction operations and non-construction operations separately on the basis it sought to limit its claim to the notified sum payable under s.111 of the Act. However, MW was entitled to defend the claim "by relying on a payment notice, setting out the basis on which no sum is due in respect of any construction or non-construction operations."
MW's Payment Notice 35 was held to be a valid payment notice and on that basis, CSL was not entitled to monetary relief it sought.
Although MW was successful in defeating CSL's claim, the Court considered MW's alternative arguments in the event that the Court had held that Payment Notice 35 was not a valid payment notice, for completeness sake and concluded that:
In this case the contractual payment provisions were compliant with the Act and applied to both construction and non-construction operations. If the contractual payment mechanism is not compliant with the Act, the statutory scheme will apply to the construction operations and the contractual payment mechanism will continue to apply to the non-construction operations. In such circumstances, a payment notice that does not separately state the sums due in respect of the construction operations will be invalid and the payer will be at risk of being liable to pay the sums applied for by the payee. The Court's judgment, particularly its findings in relation to MW's alternative arguments, highlights the importance of checking the requirements of the payment provisions in hybrid contracts. The validity of a payment notice will turn on the facts of the case and the contract requirements agreed between the parties. The Court also reminded the parties that any "payment notice must be sufficiently clear and unambiguous in form, substance and intent so that the parties have proper notice of the sum assessed as due and the basis of calculation. It is possible that a paying party who declined to apportion or allocate the sums due or deducted as between construction and non-construction operations might struggle to rely on its notice for the purposes of the Act if a deficiency in the notice undermined the validity of its global assessment."
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.