Jessica Tresham
Partner
Article
In GMC Utilities Group Ltd v Sumitomo Electric Industries Ltd [2026] EWHC 885 (TCC), Simon Lofthouse KC (sitting as a Deputy Judge of the High Court) addressed when "subject to contract" negotiations may become a binding agreement, and the interaction between the trigger to prevent release of sums in an escrow account (as agreed in a separate letter) and the dispute resolution forum within an underlying contract.
In this article we break down the High Court's decision and its implications for "subject to contract" negotiations, escrow arrangements and dispute resolution clauses.
The dispute arose out of an undersea electricity interconnector project between Pembrokeshire, Wales and Wexford, Ireland.
The key facts included:
At the heart of the dispute was the question of whether the 8 November letter constituted a binding agreement.
GMC argued that it was not binding, but merely a step in negotiations conducted "subject to contract". GMC also contended that paragraph 1 of the 8 November letter – which comprised an undertaking by GMC's solicitors to pay the escrow sum into an agreed escrow account – was an unenforceable "agreement to agree" (relying on the time it subsequently took to agree the escrow account).
The Court rejected both arguments. Applying established principles – in particular from RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH [2010], the Court found that, whilst negotiations had begun "subject to contract," the parties had eventually reached a binding agreement in the 8 November letter. The letter itself bore no "subject to contract" heading, and no such reservation appeared in any correspondence thereafter.
Moreover, the urgency of the situation - with the bond issuer expected to pay imminently - supported the conclusion that the parties intended to be immediately bound. The Court also noted that SEI immediately wrote to the bond issuer in the very terms required by the 8 November letter, further evidencing a concluded agreement.
As for the "agreement to agree" argument, the Court held that paragraph 1 was an undertaking to pay into an agreed escrow account on terms already set out in the 8 November letter itself, and there was no reason to believe the escrow account would not be established - as indeed proved to be the case.
GMC relied on the entire agreement clause in the standard conditions of the escrow agreement to argue that the 8 November letter had been superseded. The Court disagreed. The escrow agreement expressly contemplated "Supplemental Agreements" between the transaction parties - a definition that encompassed the 8 November letter - and acknowledged that the escrow agent was not bound by such supplemental agreements. Rather than superseding the earlier agreement, the escrow agreement was found to provide a mechanism for giving effect to it.
As noted above, paragraph 6 of the 8 November letter provided that if there was no agreement, adjudicator's decision, or commencement of court or arbitral proceedings on the underlying delay claims by 7 March 2025, the escrow sum would be paid to SEI.
GMC issued Part 7 court proceedings on 5 March 2025, two days before the 7 March deadline.
SEI contended that, since the sub-contract required disputes to be resolved by arbitration, "commencement of court or arbitral proceedings" in paragraph 6 referred to arbitral proceedings specifically.
The Court rejected this too. The parties were at liberty to agree any criteria to prevent the escrow sum defaulting to SEI, and paragraph 6 expressly referred to "court or arbitral proceedings" without requiring one to the exclusion of the other.
The fact that the court proceedings might ultimately be stayed to arbitration was no answer: a stay does not render proceedings void ab initio, and the court proceedings were validly commenced. The Court also observed that the escrow agreement itself anticipated release of escrow monies on receipt of an order from "a duly appointed adjudicator, court or competent arbitral tribunal," further confirming that court proceedings were not excluded.
Having found that GMC's Part 7 court proceedings did satisfy the escrow deadline, the court nonetheless granted SEI's application to stay those proceedings to arbitration under section 9 of the Arbitration Act 1996.
Applying the broad and purposive approach to the construction of arbitration clauses established in Fiona Trust v Privalov [2007], the Court concluded that all the relief sought by GMC - including declarations relating to the escrow funds - fell within the scope of disputes arising "in connection with" the sub-contract. The exclusive jurisdiction clause in the escrow agreement did not supersede the arbitration clause, since the escrow agreement was directed to the administration of the escrow sum, not the resolution of the underlying disputes.
If you have any questions about this article, please get in touch with Jessica Tresham or Sam Wallis.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.
Gowling WLG is an international law firm comprising the members of Gowling WLG International Limited, an English Company Limited by Guarantee, and their respective affiliates. Each member and affiliate is an autonomous and independent entity. Gowling WLG International Limited promotes, facilitates and co-ordinates the activities of its members but does not itself provide services to clients. Our structure is explained in more detail on our Legal Information page.
© 2026 Gowling WLG All rights reserved.