As the UK transitions to cleaner, greener energy and increased electrification, there is unprecedented demand for electricity grid connections. There are currently 307GW worth of projects in the connection queue in Great Britain.
Although dependent on location and required capacity, there are long lead times for obtaining a grid connection, whether connecting to a distribution or transmission network. As a result, grid connections have become the main determinant of timelines for the development of many generation, storage and large-scale demand projects (such as data centres).
Below we take a brief look at several recent announcements that set out the direction of travel in terms of reforming the distribution and transmission connection processes.
Firstly, in April 2023 the Energy Networks Association (ENA) – which represents energy network operators – published its action plan to accelerate distribution network connections. This sets out actions in three priority areas, as described below.
The current connection process is based on a 'first-come, first-served' model and was designed for a time when there were a smaller number of projects with a higher degree of certainty regarding planning permission and funding. However, due to the current long lead times for connections, many connection applications are now submitted well before there is certainty regarding a project's successful commissioning. This has resulted in a situation where projects that may never come to fruition are taking up places in the connections queue and potentially delaying shovel-ready projects.
In order to tackle this issue, the distribution network operators (DNOs) are proposing a partial shift to a 'first-ready, first connected' model. This means that connections which reach agreed milestones and are ready to start construction will be prioritised for connection where there is no detrimental impact on other projects ahead of them in the queue. In other words, the queue will be actively managed to maximise grid capacity.
Progression milestones were first introduced in 2017. However, connection applications that pre-date 2017 don't have milestones. Starting this spring, such projects will either be assigned milestones or removed from the queue.
Large generation or demand project connections to the distribution network are often delayed due to required transmission network reinforcement. Distribution connections are often made contingent on such reinforcement being completed. Yet, according to ENA, many distribution customers have expressed a desire to be connected early, even if there is a period during which their project will be subject to curtailment while transmission reinforcement is completed.
The Electricity System Operation (ESO) and DNOs are also working together to create clearer, more consistent technical boundaries between transmission and distribution networks, in order to better manage the connections queue and to allow small, more agile projects to connect more quickly. This should enable connections to be more easily managed within agreed technical limits at each boundary point, and variation offers will be made to qualifying customers.
The demand for battery storage project connections is greatly exceeding forecasts. ENA notes that more than 56GW of battery storage connection capacity is now in the queue – representing more than 14 Drax power stations and 200%-500% more than the ESO forecasted would be needed by 2030.
However, ENA notes that battery storage projects tend to have low capacity utilisation, as they are bi-directional in nature (sometimes importing electricity, sometimes exporting electricity and at other times not importing or exporting).
Therefore, DNOs are planning to offer battery storage operators 'non-firm' connections that allow connections to be provided more quickly. ENA is also looking at regulatory reforms and changes to technical standards to allow the more effective management of storage capacity.
ENA's action plan complements work currently being undertaken by the ESO and transmission network operators (TNOs) to speed up connections to the transmission network, such as the ESO's connections reform project and its five-point plan. The ESO's five-point plan to speed up transmission connections is as follows:
The ESO has also announced additional targeted reforms (building on its five-point plan) to speed connections, summarised as follows –
In May 2023, Ofgem issued an open letter on future reform to the electricity connections process. This letter touches on many of the same themes, initiatives and proposals discussed above, as well as some longer-term and wider-reaching reforms to the connection arrangements (such as the possibility of introducing the concept of controlled access to the connection process – either through application windows or with the introduction of stricter qualification gates).
If you need help navigating the evolving connection processes, our team of energy specialists can assist. We regularly advise a range of clients (including generators, battery developers, interconnectors and demand users) on new and existing connection offers. Please contact George Nixon or Gus Wood for more information.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.