James Stanier
Partner
Article
5
The Government, the National Energy System Operator (NESO) and Ofgem have all contributed to a considerable number of updates in recent months to bring about urgently needed grid connection reforms. The grid connection queue contains 739GW in capacity and over the last 5 years has grown tenfold in capacity and many of those projects, reportedly, do not have proper funding or necessary planning permission to progress.[1]
In 2023/2024 NESO reportedly received over 1,700 applications which far exceeds what the system requires by even 2050.[2] These amongst many other reasons has prompted the most rapid change in grid connection reform for a decade. To help keep track, we have summarised some of the key changes from the last few months.
Ofgem published an open letter setting out an overview of the next steps, including the progression of CMP434, CMP435, (see more below) CM095 and CM096 as well as its intentions to consult on the licence conditions for the electricity system operator, the transmission operator and the distribution operator. It set out the methodologies which NESO would use as part of its assessment of projects in the connections queue under Gate 2 namely: the Gate 2 Methodology, Project Designation Methodology and Connections Network Design Methodology (CNDM) and that NESO would consult later on the details.
Ofgem launched a consultation on the licence conditions to bring into effect the Clean Power 2030 Action Plan (CP2030AP) below. They said that they have tried to find a balance between a "prescriptive and non-prescriptive approach" for the Electricity System Operator licence, in how licensed parties will discharge their duties. Gate 1 and Gate 2 agreements have not been specifically defined to allow flexibility so will fall under "Bilateral Agreement and "Construction Agreement" definitions.
On the Electricity Transmission Standard Licences there would be an obligation for Transmission Owners and Offshore Transmission Owners to comply with the CNDM and support NESO with the "development and maintenance of the methodology". The consultation closed on 7 January 2025.
NESO in response to stakeholder feedback, listed projects that would automatically pass the Strategic Alignment Criteria, if they can provide suitable evidence by the end of the Gate 2 to whole queue evidence submission window. These were:
You can read more about that update here.
Following the consultation on the methodologies on 5 November 2024 which closed on 2 December 2024, NESO finally published the CP2030AP which set out its vision for how it would reach its goal that "in a typical weather year, the 2030 power system [would] see clean sources produce at least as much power as Great Britain consumes in total over the whole year, and at least 95% of Great Britain’s generation". Given the interaction between them, NESO also published its final draft modification reports for CMP434 and CMP435 and the final methodologies on the same day.
The process is set out in the CNDM :
The Gate 2 Criteria Methodology gives more detail on how projects will be assessed under Gate 2. To meet the Gate 2 Readiness Criteria outlined above they must meet the Land requirements or the Planning requirements:
Projects must also meet the Gate 2 Strategic Alignment Criteria.The project must be:
Protection Clause 1: Projects contracted to connect by end of 2026 – This will only be relevant to Gate 2 to Whole Queue assessment and not to the CMP435 Gated Application Window (for new applications under the connections reform process). This is met by the project evidencing a contracted connection date of 31st December 2026 or earlier and has met both Queue Management Milestones M2 and Queue Management Milestone M7.
Protection Clause 2a: Projects which are significantly progressed - This will only be relevant to Gate 2 to Whole Queue assessment and not to CMP435 Gated Application Window. This is met by the project evidencing planning consent (where submitted on or before 20 December 2024, a valid Contract for Difference (CfD), a Capacity Market contract (a CM Contract) or, for Interconnector or Offshore Hybrid Asset projects only, regulatory approval from Ofgem of either a Cap and Floor agreement or Merchant Interconnector approval.
Protection Clause 2b: Projects which are significantly progressed – This will not apply to assessment of initial and Gate to Whole Queue window projects. Projects must evidence a CfD, a CM contract or, for Interconnector or Offshore Hybrid Asset projects only, regulatory approval from Ofgem of either a Cap and Floor agreement or Merchant Interconnector approval.
Protection Clause 3: Projects which obtain planning consent after closure of the CMP435 Gated Application Window - This will not apply to assessment of initial and Gate to Whole Queue window projects. Projects must evidence meeting Queue Management Milestone M1, noting this must also show this was submitted to the Statutory Planning Authority prior to the closure of the CMP435 Gated Application Window and provide evidence of meeting the Queue Management Milestone M2.
The project must also be:
Users will be expected to comply with ongoing compliance requirements. For the "Land" route this includes ensuring that only 50% of the Installed Capacity is outside the Original Red Line Boundary and if it is not then the total Installed Capacity will be reduced accordingly. Under the "Planning" route a planning consent application must be made at the earliest of the queue management milestone M1 or M1 calculated forwards from the Gate 2 offer date to move from queue management milestone M3 to M1.
NESO has also outlined how it will designate projects under the reformed connections process. Designated projects form one of the options under the Strategic Alignment Criteria as well as they can be prioritised in the connection queue ahead of other projects in that Gate 2 tranche and be accelerated post Gate 2 should another project drop out of the connections queue.
NESO may designate a project that:
NESO has emphasised that it only envisages designating projects in exceptional circumstances, where a project meets the criteria detailed in this annex.
CP2303AP sets out sweeping changes to meet its 2030 clean energy objectives (which you can read more generally about here). NESO has set out capacity ranges for projects that receive connection offers for projects in and before 2030, nationally and also broken down zonally and by technology type.
The in-scope technologies are listed out as Offshore/Onshore Wind, Solar, Nuclear, Low Carbon Dispatchable Power, Unabated Gas, LDES, Batteries (i.e. batteries that do not fall within the technical definition of LDES) and Interconnectors. As devised from projections set out in Future Energy Scenario (FES) 2024, the government has also set out projected needed capacity for out to 2035 as well.
Where a project exceeds the capacity ranges, projects will have the opportunity later if other projects drop out of the queue or if the capacity ranges are increased upwards. If there is undersupply in a particular zone NESO will first look to substitute viable projects of the same technology from adjacent, over-supplied zones. Where that cannot be done NESO will reserve capacity up to the top of the capacity range.
NESO also proposes that any project with a connection date in 2025 or 2026 should retain its connection date and that projects which are over the relevant capacity ranges for 2030 should be allowed to connect in the 2035 ranges where there is capacity.
NESO will provide more details in the Strategic Spatial Energy Plan (SSEP) in 2026 including the mix of technologies.
This will not apply to projects connecting to the distribution network that are below regional thresholds for TIAs (although note that NESO is proposing increasing the TIA threshold to 5MW).
NESO published the Final Modification Report for approval by Ofgem. CMP434 is broadly designed to implement the new reformed connections process to new applications. This implements the methodologies, the bi-annual gates and the other elements of the new process into the Connection Use of System Code (CUSC). The CUSC Panel met on 20 December 2024 to discuss Workgroup Alternative CUSC Modifications (WACMs) and which should be implemented.
The Panel recommended unanimously that the Original Text and the following facilitated the Applicable CUSC Objectives:
WACMs3: This would codify a Capacity Reallocation Mechanism to allow terminated capacity to be offered to the next contracted project that has passed Gate 2 and is able to utilise the released capacity. NESO would no longer be able to utilise Project Designation or Connection Point and Capacity Reservation in respect of reallocating terminated capacity.
WACMs4: This codifies proposed restrictions on changes to project Red Line post-Gate 2.
WACMs6: This adds an obligation on NESO to implement a review of the new connections process with stakeholders to assess whether a code modification is required to codify the methodologies and guidance documents.
The Panel recommended by majority that the following WACMss better facilitated the Applicable CUSC Objectives under the CUSC:
WACMs1: Embedded Schemes which are covered by the Primary Process will be defined by capacity.
WACMs2: This creates an absolute obligation for DNOs and iDNOs to include all Embedded Projects that provide a valid Gate 2 compliance application and evidence submission within the Gated Application Window.
WACMs5: This is in line with the original proposal except it would remove Element 9: Project Designation (references to Project designation and Project Designation Methodology from Sections 11 and 17).
WACMs7: This would insert a pause for market self-regulation before the NESO/TO undertake the network assessment.
Likewise, the Final Modification Report for CMP435 was also published. This applied the connections reforms to the projects in the existing queue.
The Panel voted that the Original proposal and WACMs1 better facilitated the Applicable CUSC Objectives:
WACMs1: The compliance check, including any revised Transmission Entry Capacity (TEC) or technology change requests, would be published and a two - four week pause would be implemented for Gate 2 qualified applicants to assess their position in the queue. Applicants could then submit an application for capacity advancement, keep their project or withdraw without penalty.
NESO also announced that given the backlog of applications already in place and the urgency of any reforms, should Ofgem approve its proposals more drastic changes needed to be made. NESO announced that from 29 January, it would not accept further applications for new connection applications (with further exceptions). See here for more details.
CP2030AP makes clear that more information regarding 2035 ranges will be set out in the SSEPP which is due to be published in 2026. The CNDM has made clear however that it would not apply retrospectively to previous applications.
In the meantime, Ofgem is due to approve, reject or suggest amendments to the proposals by end of Q1 this year. If approved, the relevant Code modifications are expected to be implemented by Q2. If you have questions around grid connection reforms, our team of Energy experts can help. Please contact James Stanier for more information.
1 p.65, Clean Power 2030 Action Plan, 20 December 2024 (Main Report).
2 p.1, Open letter on "pause" to connection queue, 15 January 2025.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.