In Laing O'Rourke Delivery Ltd v Shepperton Studios Ltd [2026], the Technology and Construction Court (TCC) has provided important clarification on the interaction between payment notices and pay less notices. Amongst other things, the decision considers a point on which there was previously no clear authority: does a defective payment notice invalidate or "contaminate" a subsequent, otherwise compliant pay less notice?
We outline the background to the dispute and the TCC's judgment on this point below.
The dispute concerned the validity of payment and pay less notices issued under a building contract between Laing O'Rourke Delivery Limited (LOR), the contractor, and Shepperton Studios Limited (SSL), the employer.
The contractor had commenced an adjudication, seeking payment of £5.6 million as set out in its Application for Payment (AFP) 45.
The adjudicator found that the employer's payment notice 45 was defective, because it failed to explain the basis on which the employer's gross valuation of the sum it considered to be due had been calculated.
The adjudicator went on to conclude that this defect also rendered the employer's subsequent pay less notice invalid and awarded the contractor the full sum applied for in AFP 45.
The employer resisted enforcement, arguing that even if the payment notice was defective, the pay less notice remained valid because it clearly and properly set out the deductions being made.
The key question was whether a failure in a payment notice can "contaminate" a later pay less notice, such that both notices are invalid. The Court noted that no authority had been identified addressing this specific point.
The Court agreed that the employer's payment notice 45 was invalid, because it failed to provide a breakdown of the gross valuation figure the employer considered to be due, instead merely stating a lump sum without showing how it was calculated.
This was contrary to the requirements of clause 4.7.5 of the building contract, which required the employer to give a payment notice stating the sum it considered to be due at the due date, "calculated in accordance with clause… 4.13 and clause 4.14, and the basis on which that sum has been calculated".
An unexplained reference to earlier spreadsheets was insufficient; the detail must appear in the notice itself or in documents expressly incorporated by reference, as per S&T (UK) Ltd v Grove Developments Ltd [2018].
However, the Court disagreed with the adjudicator's finding that this deficiency contaminated the pay less notice and held that the invalidity of the payment notice did not render the pay less notice invalid.
The key reasoning was as follows:
LOR accepted that each of the three deductions in the pay less notice was sufficiently detailed. The Court held that the ability to deduct does not fall away merely because the pay less notice starts from a figure derived from a defective payment notice.
The contractual wording thus produced a result that the Court considered both textually sound and commercially sensible: the contractor received the benefit of the default payment mechanism triggered by the invalid payment notice, but the employer retained the right to make properly notified deductions.
The Court therefore held that the pay less notice was valid and effective, notwithstanding the earlier defect in the payment notice.
If you have any questions about this article, please get in touch with our Construction Team.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.
Gowling WLG is an international law firm comprising the members of Gowling WLG International Limited, an English Company Limited by Guarantee, and their respective affiliates. Each member and affiliate is an autonomous and independent entity. Gowling WLG International Limited promotes, facilitates and co-ordinates the activities of its members but does not itself provide services to clients. Our structure is explained in more detail on our Legal Information page.
© 2026 Gowling WLG All rights reserved.