Sahil Shoor
Associé
Article
(Part II.1; SS.13.1 TO 13.24)
The new Construction Act (the "Act") implements a mandatory fast-track dispute resolution process designed to get cash flowing more quickly on the projects and to reduce the cost of large and lengthy disputes.
This article sets out how the adjudication will apply to construction contracts (public and private) entered into on or after October 1, 2019 (the effective date when adjudication became mandatory) and to allow sufficient time for the new college of Adjudicators called the Authorized Nominating Authority (the "Authority") to be established, to develop a regime for the certification of adjudicators, and to certify adjudicators.
Under the Act, parties to a construction contract will be entitled to refer disputes to adjudication (based on the UK model) that flow from a proper invoice under a contract, including claims for valuation of work, services and materials and other monetary claims made in accordance with the contract, as well as set-offs, deductions and delay claims. This dispute resolution method will be mandatory on all construction projects, public and private, and all sizes and types. Parties will be free to draft their own provisions so long as the provisions are consistent with the Act.
Adjudication is similar to a mandatory arbitration and will provide a fast means to get an interim decision by an adjudicator of any matter that falls within Part II.1, of the Act and if one party is not satisfied with the adjudicator's decision, the party can proceed with a court action or an arbitration to reverse what the adjudicator has decided. In the interim; however, the adjudicator's decision must be followed immediately. Moreover, the adjudication may only address a single matter unless the parties to the construction contract/adjudication and the adjudicator agree otherwise.
The following disputes can be adjudicated:
A party to a construction contract can only commence an adjudication against a party with whom it has a contract. An adjudication has to be started before the date the construction contract between the parties is completed, unless the parties to construction contract agree otherwise. A party who wishes to refer a dispute to adjudication gives the other party a written notice that includes:
The Act states that the adjudicators will not need to have a legal background, but likely will include members of a regulated profession such as architects, quantity surveyors and engineers.
The parties to a construction contract are prohibited from agreeing on the adjudicator in advance. The Act states that there is a 4 day deadline for the adjudicator to agree to take on the adjudication, which implies that the parties to a construction contract have to agree on the adjudicator prior to that.
If the parties cannot agree on an adjudicator, or the adjudicator does not agree to conduct the adjudication, within four days of the notice of adjudication, then the referring party must request the appointment of an adjudicator by the Authority, and the Authority must make the appointment within seven days of receiving the request.
Within five days of the selection of the adjudicator the party who started the adjudication must provide a copy of the contract in question, and any documents the party intends to rely on to the adjudicator. The adjudicator must release his/her written decision within 30 days of receiving the documents. The adjudicator can request up to 14 additional days, but the adjudicator's request can be refused by either party.
These timelines provide that absent an extension of time, the adjudication will be determined within 46 days of the adjudication being commenced. Once the adjudicator has made a determination, a party required to pay must do so within 10 days.
The adjudication is subject to the adjudication procedures set out in the construction contract (if they comply with Part II.1 of the Act). However, if the contracts do not address adjudication procedures, or if the procedures set out do not comply with the requirements of Part II.1 of the Act, then the adjudication is subject to the adjudication procedures set out in the Act governs.
The adjudicator may conduct the adjudication in a manner he/she determines to be appropriate in the circumstances, and shall conduct the adjudication in an impartial manner. The adjudicator shall make a determination of the matter no later than 30 days after receiving the documents required in the notice of arbitration. The time may be extended at the adjudicator's request and with the written consent of the parties for a period of no more than 14 days, or upon written agreement of the parties, and subject to the adjudicator's consent. Otherwise, if it is made after the determination date, it is of no force or effect.
An adjudicator may exercise the following powers and any other power of an adjudicator that may be specified in the contract or subcontract:
The parties to the adjudication will each be responsible for an equal share of the adjudicator's fees, and each party will bear its own costs, regardless of the result. However, the adjudicator may exercise his discretion and award costs against another party, if the adjudication makes a finding that the party acted in a manner that was "frivolous, vexatious, an abuse of process or bad faith".
Once the adjudication is completed, either party to the adjudication can bring an application to the court for an Order enforcing the adjudicator's determination. Once the court order is made, it can be enforced like any other court order, including by way of writ of execution or by garnishment.
Additionally, if an adjudicator's decision to pay is not obeyed, the party expecting the payment would be entitled to suspend work under the contract or terminate. In the experience of the UK, only a small number of cases typically go from the adjudication to litigation or arbitration.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.