Sue Ryan
Partner
Article
7
In the second of our mini-series on insolvency in construction, we consider what you need to do when you find out that the party you are in contract with has become (or is about to become) insolvent.
The first thing you should do in the event of a counterparty's alleged insolvency is check which legal entity you are in a contract with.
This is in order to prevent you from acting too early and committing a repudiatory breach yourself, if you take pre-emptive action against your counterparty.
Information is available through a variety of sources including searches of the public registers at Companies House and at the courts or credit agencies. Alternatively, if you believe an Insolvency Practitioner has been appointed, you can contact him or her for confirmation.
You should be aware that absent a specific contractual right, insolvency is not a breach of contract under English law. You cannot therefore simply rely on a right to terminate for default or breach - express wording dealing with insolvency is required.
Standard form contracts do not generally provide for automatic termination on insolvency. Most construction contracts do however provide a right to terminate the contract upon the employer's or contractor's insolvency. You should check how widely the contract defines insolvency for these purposes as well as the procedure to be followed. It is important to check that the particular circumstances involved constitute insolvency as defined by the contract.
Getting this wrong (whether or not those specific events have occurred and/or the correct procedure to follow) could give rise to wrongful repudiation of the contract, termination rights and a claim for damages - which may, for example, include loss of profits on the overall project, or the cost of engaging others to complete the works and claiming the difference from you.
It generally pays to plan for the worst case scenario. Check whether the contract deals with insolvency and its consequences. This will include for example:
Every contract is different and many are likely to be subject to bespoke amendments.
Ideally "Insolvency event" should be defined widely enough to catch events which occur before the formal insolvency process begins such as winding-up petitions being issued or a notice of intention to appoint administrators being filed.
As a starting point, the standard form contracts listed below define insolvency and set out the relevant procedure as follows:
A company:
An individual or partnership:
The employer can terminate the contractor's employment at any time.
The contractor's works obligations are suspended from the date of insolvency. Whether or not termination occurs, payment stops until after completion of the works and making good defects.
If the employer terminates, it may take possession of the site and employ others to carry out and complete the works. The contractor cannot hinder or delay the taking of these measures.
The employer will have to pay the contractor the balance due, if any, upon completion of the works by others.
The contractor can, by notice to the employer, terminate the contractor's employment.
Whether or not the contractor terminates, as from the date the employer becomes insolvent, its obligations under the contract to carry out and complete the works are suspended.
The contractor should prepare an account and provide it to the employer within two months. The employer must pay the contractor any amount due within 28 days of submission of the account.
Check the terms of any contract with the supply chain including for example:
If the company has provided collateral warranties, these may include step-in rights by the employer. If step-in rights are included there may be a number of additional considerations. Step-in provisions allow the employer to step into the shoes of the contractor if the contractor becomes insolvent.
The ability to step-in should be exercised with caution - you should be aware, for example, that often you will take on liability for any outstanding or unpaid amounts.
Carefully check the notice provisions in your contract so as to ensure you follow the correct procedure. You want to avoid a situation where a technical point is raised as to the validity of service.
In our next article in the series we look at the practical issues associated with insolvency.
Insolvency is a complex and specialist area of law, so if you do need advice on these or any related issues, please contact Sue Ryan or one of our Restructuring & Insolvency experts.
Footnotes
[1] The Joint Contracts Tribunal Limited (JCT), Design and Build Contract, Thomson Reuters, 2016.
[2] The Joint Contracts Tribunal Limited (JCT), Design and Build Contract, Thomson Reuters, 2011.
[3] NEC3 Engineering and Construction Contract, 3rd Edition Reprinted with amendments 2013, Thomas Telford Ltd, 2013.
[4] NEC4 Engineering and Construction Contract, 4th Edition, Thomas Telford Ltd, 2017.
[5] Conditions of Contract for Plant and Design-Build: The Yellow Book, Second Edition, The International Federation of Consulting Engineers (FIDIC), 2017.
[6] Conditions of Contract for EPC/Turnkey Projects: The Silver Book, Second Edition, The International Federation of Consulting Engineers (FIDIC), 2017.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.