A force majeure clause typically operates to give a party relief from its obligations when there is an event outside the control of that party which prevents or delays performance of those obligations. Traditionally, to qualify as force majeure such events have had to be extreme- such as natural disasters or wars. However, critically, the effect of these clauses is determined by what the clause actually says.
This alert is intended as a reminder of the importance of Force Majeure clauses and their content. Not all force majeure clauses are the same- they can be broad or narrow in scope and serve one party better than the other. Importantly, English law does not imply force majeure terms and will only apply doctrines like frustration in rare circumstances where performance is impossible, making it a far narrower route to relief.
A force majeure clause is particularly important for suppliers as it can offer protection where performance is disrupted or becomes difficult due to external influences and market factors (e.g., export bans, port closures, raw material shortages, cyber security incidents). Without such a clause, a supplier may be in breach of contract and face a damages claim and/or termination even if non‑performance is genuinely beyond its control.
A supplier is typically motivated to seek a widely drafted definition of force majeure as it has the majority of the performance obligations and is most likely to be negatively impacted by various factors- this may, for example, include industrial action by the supplier's own employees/agents/subcontractors or issues in its supply chain.
A customer, on the other hand, usually wants to keep the force majeure definition as narrow as possible and either to an exclusive list of specific events or to events that are outside the "reasonable control" of the supplier. A well-advised customer would certainly want to exclude areas a supplier can control with sufficient oversight of its business.
It follows that negotiation of the definition of "force majeure" should not be overlooked and can become quite contentious. Indeed, a customer who only has an obligation to pay may not want to include a force majeure clause at all and may wish to leave it as a supplier risk.
It is, though, standard market practice to include a force majeure clause in commercial contracts. And if a clause is to be included, careful drafting creates greater certainty and allows an element of planning, structure and control should the relevant circumstances arise.
Well-designed clauses can require prompt notification, reasonable endeavours to overcome the event, clear evidential standards so that the non-affected party can assess impact and engage contingency measures and ultimately a mutual or unilateral termination right where the force majeure has affected performance for a specified period. They can also allocate cost between the parties- for example, dealing with the customer's liability to continue to pay the charges where performance is suspended and each party's liability for the other party's costs of dealing with the force majeure.
If a contract is silent on force majeure, a possible fallback is frustration—a high bar that discharges the contract entirely only where performance becomes impossible or radically different. For most disruptions that a party would be seeking to cover under a force majeure clause (including increased cost or supply chain bottlenecks), frustration will not apply, leaving the affected party exposed.
In RTI Ltd v MUR Shipping BV (UK Supreme Court, 2024) the Court confirmed a requirement in force majeure clauses that the relevant circumstances cannot be overcome by using “reasonable endeavours”, to do so does not require acceptance of non‑contractual performance (i.e. in this case payment in a Euros rather than US dollars). The decision reinforces the principle that in contractual disputes what the contract says is paramount and that workarounds outside the contract are not required.
In Seadrill Ghana Operations Ltd v Tullow Ghana Ltd (Commercial Court, 2018) the Court clarified that, to be relied upon, the force majeure event must be the sole reason for non-performance, not one of many. Where a party’s own contractual or commercial choices contribute to non‑performance, force majeure relief may be unavailable.
In Canary Wharf (BP4) T1 Ltd v European Medicines Agency (High Court, 2019) although a frustration case, the decision highlights that changes in circumstances (i.e. Brexit in this case) rarely discharge contracts under English law under the doctrine of frustration. It reinforces the importance of including express force majeure/change‑in‑law provisions rather than relying on frustration.
If you'd like to discuss any of the issues raised in this article or commercial contract support more generally, please contact David Lowe, Rachel Pennell or Katharine Graff for bespoke, expert advice.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.
Gowling WLG est un cabinet juridique international constitué des membres de Gowling WLG International Limited, une société à responsabilité limitée par garanties enregistrée en Angleterre, ainsi que leurs affiliés respectifs. Les membres et affiliés constituent des entités autonomes et indépendantes. Gowling WLG International Limited promeut, facilite et coordonne les activités de ses membres, mais ne fournit pas elle-même de services aux clients. Pour en savoir davantage sur notre structure, consultez notre page Avis juridique.
© 2026 Gowling WLG Tous droits réservés