Brett Mason
Senior Associate
Article
In Mulalley & Co. Ltd v Sto Ltd & Sto SE & Co. KGaA [2026] EWHC 1552 (TCC), the Technology and Construction Court (TCC) assessed quantum on a contribution claim brought by a main contractor against the German parent of a cladding system supplier, following a default judgment that the parent had not defended.
The judgment provides a worked example of how courts quantify remedial costs and contribution in post-Grenfell cladding claims under the Building Safety Act 2022 (BSA) and the Civil Liability (Contribution) Act 1978.
Since the Grenfell Tower tragedy, main contractors who have settled cladding claims increasingly seek contributions from product suppliers. The BSA provides two key mechanisms: s.149 contribution claims and s.130 Building Liability Orders (BLO) (allowing liability to be imposed on an “associated” parent company where the direct subsidiary cannot meet it).
Here, Mulalley’s UK supplier (Sto Limited) entered administration in January 2025, so Mulalley pursued a BLO against the German parent, Sto SE & Co. KGaA. Sto Germany did not acknowledge service, file a defence, or participate at any stage. The TCC entered default judgment on 8 December 2025 for damages to be assessed.
All findings about the product’s defects and Sto’s conduct arose because the default judgment was not contested, they were not tested at a merits-based trial. On an assessment of damages after default, the Particulars of Claim act as “a proxy for the judgment, setting out the basis of liability” and the defendant cannot dispute that basis. The claimant must still prove quantum by evidence.
In 2006, Chelmer Housing Partnership engaged Mulalley under a design-and-build contract to refurbish Parkside Court, Chelmsford (a 54-flat tower block and new 27-flat podium), including design and installation of external cladding.
Mulalley subcontracted the cladding works specifying the StoTherm Classic K system. Post-Grenfell, Chelmer identified defects. Mulalley settled with Chelmer on 22 December 2022, agreeing to remove and replace the entire cladding system and pay sums to Chelmer. The system was fully removed.
The unchallenged pleaded case (deemed established via the default judgment, which Sto Germany did not contest) alleged: Sto failed to supply a product complying with Building Regulations functional requirement B4(1) and regulation 7, made misleading statements, and the system was inherently defective, causing the flats to be unfit for habitation.
The Court assessed quantum across four issues.
First, expert evidence assessed total costs at £3,431,633.53 (a reduction of approximately £302,000 from the gross claim of £3,733,837.96), which the Court accepted.
Second, on causation, the defective Sto render system accounted for 85.83% of tower external wall works and 69.03% of overall development works. After applying these percentages and stripping legal costs, recoverable loss was determined to be £2,025,499.62, which the Court accepted.
Third, on reasonableness, there was no evidence of unreasonable expenditure and no alternative technical solution was identified. The Court noted that Mulalley had a direct financial interest in efficiency and avoiding gold plating and accordingly accepted the costs as reasonable.
Fourth, turning to contribution under section 2(1) of the Civil Liability (Contribution) Act 1978, the Court assessed what would be a “just and equitable” contribution. Counsel compared Sto to an architect responsible for a design defect (which typically attracts contribution in the range of 67–80%). Based on the unchallenged default-judgment findings, the Court found that the principal cause of the defect was that Sto’s standard detail included a layer of combustible insulation over fire barriers. The Court assessed contribution at 87.5%, resulting in a judgment of £1,772,312.17 plus interest.
s.130 building liability orders can reach overseas parents. Where a UK subsidiary is insolvent, the BSA provides a route to the parent with significant financial consequences if the parent does not engage. From a claimant’s perspective, this extends recovery options beyond the immediate contracting party and may incentivise earlier settlement discussions.
For overseas parent companies, however, this creates potential exposure that may not have been anticipated when structuring UK operations and raises questions about the scope of “association” and the adequacy of procedural safeguards when claims are pursued across jurisdictions. Manufacturers and suppliers may wish to review corporate structures and insurance arrangements in light of this extended reach, whilst claimants should factor the availability of Building Liability Orders into their litigation strategy.
Failing to defend resulted in all pleaded allegations becoming established and a contribution of 87.5%, (an amount above typical architect design-liability ranges). Parties served with BSA claims should note the cost of inaction.
The judgment provides a practical template:
The findings about the StoTherm Classic K system and Sto’s conduct arose solely from an uncontested default judgment against a non-participating parent. They were not the product of a contested trial. The position could be materially different where a supplier fully engages.
If you have any queries on this article, please get in touch with Brett Mason.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.
Gowling WLG est un cabinet juridique international constitué des membres de Gowling WLG International Limited, une société à responsabilité limitée par garanties enregistrée en Angleterre, ainsi que leurs affiliés respectifs. Les membres et affiliés constituent des entités autonomes et indépendantes. Gowling WLG International Limited promeut, facilite et coordonne les activités de ses membres, mais ne fournit pas elle-même de services aux clients. Pour en savoir davantage sur notre structure, consultez notre page Avis juridique.
© 2026 Gowling WLG Tous droits réservés