Good afternoon. So welcome to session 4 of From Bids to Bricks. On behalf of myself, Jessica Foster from Gowling WLG and my co-chair Kyle David from Aon, we want to extend a warm welcome to all of you joining us today. Thank you so much for making time in your busy schedules to attend. Your support and engagement is truly what makes this series possible and we appreciate it. Kyle.
KYLE DAVID: Hello. As Jessica mentioned, my name is Kyle David and I work with Aon supporting public sector clients across the country. I'm happy to be here today as part of the Bids to Bricks series. Before we begin, we can go to the next slide.
There are a few housekeeping items to address. Please note that the session is being recorded and you can ask questions at any time by clicking the Q&A icon at the bottom of your window. As we have in the past, we have reserved the last 15 minutes of the presentation today to answer any questions that you may have.
Friendly reminder. Similarly, as we have in the past, that if you miss anything today, that the session being recorded will be available approximately one week after the session. Also for any lawyers in the room, this program is accredited for up to 1.5 substantive CPD and CLE hours.
And following today's sessions, you will be receiving a feedback survey. I encourage each of you to please take a moment to fill this out, as it's going to ask questions regarding the content. And we, obviously, want to be ensuring that we're presenting the most relevant and informative content to those that are attending. You can go to the next slide.
Finally, we have our legal disclaimer. This presentation is for information purposes only and is not legal advice. Our Gowling's colleagues would be pleased to discuss specific legal matters offline. On to the next slide.
Today's session is the fourth installment of our seven-part webinar series and is titled "Don't Let liens hold you back-- know your rights and risks under the Ontario Construction Act and lien legislation in Alberta and British Columbia." Over the next hour and a half, we'll do a deep dive into the key considerations related to construction liens holdbacks, payments requirements across Ontario, Alberta, and British Columbia.
We have three more sessions coming up in 2026, as shown on the slide, with our next webinar on October 27 focused on environmental liability insurance and bonding. Feel free to scan the QR code, which will take you to our registration page, where you can sign up for any of the remaining sessions. And with that, back to you, Jess.
JESSICA FOSTER: Great. Thank you, Kyle. OK. I won't spend too much time on this slide. As Kyle already said, we're going to be talking about liens before moving to holdbacks, construction trusts, and finishing with prompt payment. And then, of course, some questions at the end.
And of course, all of these topics are going to be covered from the Ontario, Alberta, and BC perspective, which in addition to hoping that you find this beneficial, I think it will be also very interesting and enjoyable for you.
So with that, I'd like to next introduce my Gowlings colleagues who will be presenting today. Ted Betts is the head of Gowlings infrastructure and construction sector group and also leader of the firm's nuclear sector group.
He's been practicing in the construction and infrastructure sectors for more than 25 years and is certified by the Law Society of Ontario as a specialist in construction law. Ted is repeatedly recognized as a leading project lawyer by Chambers, Canadian Legal Lexpert Legal 500, and many other industry and peer groups. And we are very grateful to have him here with us today.
Aaron Hunter is a Toronto based partner in Gowlings infrastructure and construction group. Aaron has extensive experience in structuring, drafting, and negotiating complex commercial contracts, with a focus on the development of major capital projects.
Prior to joining Gowling, Aaron served as in-house counsel at two global engineering firms in a hybrid legal business role at a large Canadian mining company. Aaron and Ted will be co-presenting the Ontario elements of the webinar today, with Ted even dipping his toe into some of the Alberta elements, I am told.
Tom Brookes is not only a partner in our Calgary office at Gowlings with an incredibly busy construction law practice, but in all of his spare time, Tom teaches construction law at the University of Calgary faculty of law. We are very pleased to have Professor Brookes joining us today to speak to the Alberta elements of the webinar.
And finally, last but certainly not least, Jeremy Sapers is a litigation and dispute resolution partner in Gowlings Vancouver office, and also a member of the construction and infrastructure, environmental law, and commercial litigation groups at the firm.
Not only is he called to the bar in British Columbia, but he's also called in Alberta and Yukon, and has represented clients before all levels of courts, including the Supreme Court of Canada on an application for leave. A big thank you to Jeremy for joining us today from BC and to all of our presenters. I'll now turn it over to my colleague Ted to get us started.
TED BETTS: Great thank you. So welcome everybody. We're going to spend the next while talking about some of the basics of construction lien laws, which are consistent-- relatively consistent across the country outside of the Civil Code in Quebec.
We are going to focus on Ontario, Alberta, and BC, where we have offices, but we have lawyers called in every jurisdiction in the country and are able to address any questions that you have on any construction matter anywhere in the country.
Construction laws are established by statute. They create a unique regime for construction projects that provide specific rights that are statute-based. And so you really do need to look at the statute to look at those specific rights. They don't exist at common law. They don't exist in the natural general commercial laws. They exist because they're written down in statutes in each of the provinces.
And so we're going to look at some of the key ways that those statutes protect payments to contractors and consultants in the construction industry. We're going to look at the specific rights that are granted for what we call lien rights, holdbacks-- that's payment with retainage on payments that are made. Construction trusts. And we'll close out on prompt payment-- the newest addition to the suite of protections provided to contractors on projects.
Equally important for owners and contractors to know all of these rights. They provide detailed procedures for payments, for disputing payments, and they're set out in the statute as well. These cannot be contracted out of.
So it's important to understand those rights and where the limits of the contract bumps up against the unalterable rights that are set out in the statute. We have a lot to cover. So let's get going. Over to you, Aaron, to start talking about liens in Ontario.
AARON HUNTER: Thanks, Ted. So I'm an Ontario guy for the purposes of this presentation, but I'm going to start off with just one general slide about liens to introduce the concept of a lien. Simply put, a lien is a remedy for non-payment that, as Ted mentioned, is created by a statute, a provincial statute.
And it's specifically for construction work and for players in the construction ecosystem or the construction context. So a remedy for non-payment. If you're say a contractor and you are owed $10,000, you have a claim for $10,000, a lien is not the claim itself. The $10,000 is your claim.
The lien is security for your claim. It's a remedy that will hopefully help you with your claim. And again, created by statute. If it weren't for the statute, you wouldn't have this extra remedy at all. Next slide, please.
So who can lien? We can ask that in other ways. Who has lean rights? Who is entitled to lien? You have lean rights. If you are supplying services or materials to what the Construction Act in Ontario-- now we're getting into the Ontario specific content here, with the Construction Act in Ontario calls an improvement.
And, as you can see on the slide, there's a big definition of improvement from the statute. But for everyday purposes, you can think of an improvement as a construction project. And it could be small or large. It could be any size, any value. Something as simple as renovating a bathroom in a house or something as big and complex as designing a multi-billion dollar stadium for a city.
We'll look at the definition of improvement briefly. It's quite broad, as you can see, but there are always people trying to push the boundaries of it. There's a lot of case law in Ontario, at least, on whether something does or does not count as an improvement. And I'll speak a bit about that case law later.
But just as a preview, it's more likely to be seen as an improvement if what you're doing is a sort of a direct and essential contribution to a construction project. And you're it's more likely to be seen as an improvement if what you're doing enhances the value of the land and has a sort of sense of permanence or attachment to the land.
So it can be quite a gray area or an interesting analysis sometimes whether something counts as an improvement or not. And it's important because if it's not an improvement, there won't be any lien rights.
And if you do have lien rights, technically speaking, they exist from the beginning of your work, from as soon as you start work, the lien exists. It's just passive. It's called a subsisting lien. And it doesn't really do anything, and nobody cares about it until there's non-payment, there's a claim, and somebody registers or threatens to register a lien when the lien is, I guess, activated. Next slide.
I'd like to pause and say something specific about a part of the definition of improvement about capital repair. Before 2018, when construction law in Ontario went through some big changes, the old statute said that repairs counted as an improvement, but this caused some confusion and problems.
And so in 2018, the government amended the law to make it clear that there's a distinction between what's called capital repair and every other kind of repair. So a capital repair, which extends the normal economic life of a facility or improves the value or productivity of the land or building, that counts as an improvement.
But every other type of repair you can imagine does not count as an improvement. And so doing that repair, supplying services or goods to that repair does not give rise to lien rights. And I mean, I still think the distinction is-- there's some gray in there, but that's an important feature of the new definition of an improvement. Next slide.
So the Construction Act distinguishes also between a contractor who has a contract and subcontractors who have subcontracts. So if you think of construction as a sort of pyramid with the owner of the land or building at the very top of the pyramid, the first kind of notch between the owner and the contractor, we would call that the prime contractor, that is called the contract in the Construction Act, only that one between the owner and the first level contractor is the contract.
And everything that is below that is a subcontract involving subcontractors. And the key point I need to make about this slide is that wherever you are on that pyramid, you might be the contractor sitting right underneath the owner. Your contract is directly with the owner. You might be a subcontractor three rungs down.
You have lean rights if you are supplying materials or services to an improvement. And in fact, it's more important the farther down the pyramid you go, because it's subcontractors who are the most vulnerable and need the protection of the statute because they have no privity of contract with the owner of the land. They can't sue the owner for non-payment. So they're the ones, the subcontractors who really benefit the most from this remedy. Next slide.
So, what does the lien attach to? I think I need to approach this by talking about the concept of the owner. So the Construction Act uses the term owner in a couple of different ways. The owner is the person who hires the contractor in the prime contract. That's one sense that the term owner is used in.
But the other sense is the owner or owners are-- it's anyone who has an interest in the land. So it's easier to do this by way of example. Imagine a retail space. There's a landlord who owns the retail space and enters into a lease with the tenant. And the tenant then turns around and hire someone to perform some construction work in that space.
So that tenant fits within the definition of owner for certain purposes. But if there ends up being a non-payment situation and the construction contractor makes a claim and then registers a lien, it goes not against just the interest of the tenant in that retail space, but against the interest of what we think of as the true owner, the landlord.
So that lien would end up attaching to the landlord's interest, which is one reason why everyone is so keen to avoid liens being registered on Title. And I just want to leave you with the key point that no matter where you are on the construction pyramid or ladder, if you register a lien, it goes right up to the top or right up to the bottom, however you're picturing it to the land, to the Title for the land.
And on this slide, I think that's all that I want to cover on this slide. Continuing with, what does the lien attach to? There are special rules for public properties or land and buildings owned by public entities.
The lien in this case does not actually attach to the crown's or municipality's interest in those premises. There are policy reasons and other reasons why that wouldn't be workable for people to be able to put liens on public property.
But if you're a contractor or subcontractor and you haven't been paid, you still can lien. But instead of being a charge on the land, it's now a charge on the holdback. And I know we haven't talked about holdback yet, but some of you will be familiar with it anyway, and we will talk about it a little bit later. Next slide. Oh, now I'm going to hand off to Tom to discuss lien basics for Alberta.
TOM BROOKES: Thank you very much, Aaron. And thank you all for attending. Good afternoon. Once more, I'm Tom Brookes, and I'm speaking to the Alberta legislation. A lot of the Alberta legislation is similar in concept to Ontario. That is, that builders liens attached to the, quote, "interests" of the, quote, "owner.
What that means is, therefore, that the, quote, "owner" is not necessarily the landowner, rather that they have to satisfy three elements that are quite consistent with the Ontario legislation, namely, that they have to be a person who has an interest in land and who requests impliedly or expressly the work.
And that such work is performed on their credit, on their behalf, or of their property and consent, or for their direct benefit. And lastly, that the work that is performed is done on that particular land for the purposes of an improvement.
This is to say that if all three of these elements are satisfied, someone can be an owner. But it is to say that those who, for example, don't impliedly or expressly request the work may not be considered an owner, and so therefore, are not subject to the lien.
A good example of this is a landlord who's lessee requests work, of which the landlord has no involvement and is unaware. In those cases, the landlord's interest in the land is not encumbered by a lien registered in respect of the work for the lesee of the land. This holds the principle, essentially, that one ought not to be liable for a lien for work that you didn't request, but whether you requested it is a nuanced question. Next slide, please.
So on this slide, I'm going to talk about the exceptions and the special cases to what I just mentioned. So firstly, for the purposes of a lien, there can be multiple owners because multiple sets of people may have interests in land and multiple may have impliedly or expressly requested the work to be performed.
One exception to this is the crown. The crown is not subject to a lien claim. However, the rights of an estate in the land of the Crown, so for example, a tenant or a lessee, can be the subject of a lien, but in those cases, the lien purely attaches to the leasehold interest and not once more to the Crown's interest. This upholds the principle that one can't essentially compel the sale of the Crown's land if the lien is realized in court.
Liens, however, can be registered against municipal land. So this leads to the nuance that you can register liens, for example, on the city of Calgary's property, but not on the province of Alberta's property and not on the government of Canada's property.
In addition, one cannot register liens against highways or irrigation districts, again, once more, for the principle that you would not want to be able to compel the sale of those kinds of lands. And lastly, for the reasons of federal paramountcy, a lien cannot be registered against an Indian Band's interest for the reason that they are federally regulated.
However, if there is a leasehold interest in the Indian Band's land, then you can register a builder's lien against that leasehold interest. Next slide. I'll pass then to Jeremy Sapers, who will be speaking to the British Columbia legislation.
JEREMY SAPERS: Thanks, Tom. Good afternoon to everyone in Ontario. And still good morning to those of you in Western Canada. My name is Jeremy Sapers, and I practice out of the Vancouver office and will be discussing the lien legislation in British Columbia.
We'll find that there's a lot in common between British Columbia, Ontario, and Alberta. So what I'll spend most of my time on is highlighting any key differences that it's important to understand for British Columbia.
In that province, lien holders can claim a lien against the improvement, which is the defined word in the BC lien legislation. That really just means the project. You can also have a lien against the land, which is where the project is being developed.
Your lien also attaches to any material or equipment that is supplied to the land. And I'll skip the second last bullet-- I'll come back to it. The last bullet there is that you can also have a lien against the security.
And this is foreshadowing a topic that we'll get into a little later on in the presentation. But once a lien is registered and if the lien needs to be discharged or removed from Title because it's causing a problem for the owner, the owner can deposit security in place of the lien. And when that happens, the lien no longer attaches to the land and instead it attaches to that security.
The second last bullet there, the holdback. This is a key difference in British Columbia. It's the only jurisdiction where the statute creates a second type of lien against the holdback. Ted mentioned a little bit about the holdback. This is the retainage.
So these are the funds that are withheld from each progress payment. And in BC, there's this it's important to know there's this second type of lien with a unique mechanism. And it attaches to the holdback funds. Next slide, please.
The definition of improvement. As I said, this is really just another word for the project. It's quite broad and it's very similar to the definitions that we saw in Ontario and Alberta. It's on the slide there. I won't read through it, but it is very broad and it really covers any type of construction work.
In BC, we do not distinguish between repair or maintenance work and often work that is repair work that might be excluded in places like Ontario, it can be the subject of a lien in British Columbia. Next slide, please. Back over to you, Ted or Aaron.
AARON HUNTER: So I'm going to reprise the topic of, who can lien in Ontario.? I did speak about this briefly a minute ago, but it's so important that I'll expand on it a little bit now. So as a reminder, you have lien rights if you are supplying services or materials to an improvement or rather a project. We've talked a little bit about what improvement means. Now I'll talk about supply of services and materials. Next slide, please.
So a contractor might ask a question, I've done some work at a place on a project. Do I have lien rights? And the answer or the start of the answer is not every kind of work gives rise to lien rights. And there is, at least in Ontario, a great deal of case law saying, yes, that has lien rights. Yes, that looks like it should have lien rates. That doesn't seem like something that should have lien rates. That one definitely doesn't. And I'll touch on some examples.
So if your business is renting equipment to people, like let's say a bulldozer and then they use it for a construction project, then the renting of the equipment is lienable. Also very different example, but if you're an architect or an engineer and you're doing plans, drawings, specs that enhance the value of the owner's interest in the land, that is likely to be considered lienable.
And you, as the architect or engineer, can exercise your lien rights. In the case law, the principles that seem to emerge that suggests you have lien rights are the directness of your contribution to the project, to the construction, the permanence or attachment. Things that are temporary are less likely to attract lien rights.
This idea of enhancing the value of the land. And, I mean, how close is it, sort of, intuitively to what we think of as construction work? There are some things-- I'll just give you a couple of examples of things that do not give rise to lien rights. Snow removal is one from an Ontario case, million rights.
And another one is installation of blinds or curtains, it's not considered integral, permanent, direct contributing to the improvement in any kind of lasting permanent sense. So liens are not a remedy for everyone who's owed money by somebody else.
They're meant for people and companies in the construction industry. So there's been a lot said and written and decided by courts on this exact topic. Next slide, please. Oh, I'm going to hand it back to Tom to talk about Alberta once again.
TOM BROOKES: Thank you, Aaron. Alberta has a lot of similar characteristics. So I won't regurgitate them too much. On the slide, you see the list of potential claimants and a lot of them are very similar. So we have our contractors, we have our suppliers, we have those who provide materials, we have those who provide services. Conceptually, any of these categories can be subject to a builder's lien.
That being said, the limitation typically is whether or not there is an improvement, whether or not the work is temporary. And so you get some fringe cases, for example, where, for example, a kitchen at a remote improvement was considered to be entitled to a builder's lien on account of the fact that it was so intrinsically related to the work being performed. That is to say, it was so remote that the kitchen was needed to feed the workers.
Architects and engineers can also be a fringe case. The principle there is a little bit different than Ontario. In Ontario, the test is not whether their plans enhance the value of the land, but whether the plans themselves were intrinsically a part of the work that was in fact performed.
So that kind of test omits, for example, plans of an architect that aren't acted upon and don't end up in the work, or things like pre-construction feasibility studies, which can be performed but aren't directly related to the actual physical work that's performed, but are something that's preliminary and aren't necessarily targeted towards any particular form of construction. Next slide, please. I'll turn it over to Jeremy once more and he'll speak to the British Columbia situation.
JEREMY SAPERS: Thanks, Tom. Again, as with the earlier slides, who can lien in British Columbia is quite similar to who can lien in Ontario and in Alberta. In BC, if you are a contractor or a subcontractor or a worker-- and those are all defined terms, and I'll discuss them in just a moment. If you're any of those three participants in the construction project and you performed work or you supplied material to an improvement, then you have a claim of lien.
And again, you have that claim of lien not only against the land and the improvement, but you have a lien against any holdback that was retained by a party above you in the contract pyramid. Similar to Alberta architects, engineers, design consultants are entitled to liens.
And there's a fair bit of case law in BC about work that those participants perform for projects that never get underway. And what those cases say is that there actually has to be a physical change to the land in order for the pre-construction work to give rise to a lien right.
So if a design consultant architect engineer does pre-construction work, feasibility studies like Tom mentioned, and then the project never gets off the ground, or the project changes and those designs are never used and incorporated into the improvement, then those architects, engineers, consultants, they don't have lien rights.
So we've been talking about lien so far in a fairly abstract way. But now we'll switch to procedure, and what do you actually do when you want to exercise your lien rights? So as I mentioned, your lien rights exist from the moment you start work.
But at a certain point in time, if you're owed money and you're not being paid and you want to do something with that lien, you want to activate it as a remedy to help you get paid, what do you do? Well, in Ontario, at least under the Construction Act, you need to deliver what's called in the Construction Act written notice of a lien to the payer. And the payer means the person that you have a contract with.
I won't dwell on much in the rest of the slide, but the contents of that notice and the form of that notice are spelled out in the Construction Act. And once the payer receives that written notice of a lien from you, that triggers certain obligations on them that-- I don't know that we've got time to go into it in detail, but that's the first step. Next slide.
And in addition to providing the written notice of a lien, the other step that you take on the early side in the process is to preserve it. And that's a lovely, archaic sounding legal term to preserve the lien.
But you do it in a very modern way. You do it electronically in Ontario, at least through the land registry office. You register it on Title. And then afterward, you have to take another step, also kind of archaic sounding, you have to perfect it. But I'm going to stop there because Ted will talk about the perfection of liens a bit later in Ontario.
TED BETTS: I'll jump in once more on behalf of Alberta. So Alberta, unfortunately, is not quite so sophisticated as Ontario, at least in the aspect that they still have to use paper instead of purely electronic.
The simple answer to, How do you lien? is I would suggest firstly, talk to a lawyer. It's important to get it right. But as a brief recitation of the things that you must do, you have to first find the correct Title in order to know which one to lien. This is important because if you select the incorrect land Title to lien, you won't have a valid lien, and the lien to which your land attaches won't be valid at all.
This requires some searching both of the landowners, you might have to look through tax searches. It often isn't in the contract itself, and so does require often technical expertise and some digging to find the correct form of land.
Once you have ascertained the correct land Title description, registering a lien is as simple as completing the form. This is form A. It identifies the land that is going to be the subject of a lien, the dollar value, it identifies the owner or purported owner, and it identifies the lien claimant.
This is all sounding relatively simple. And indeed, this is one of the important aspects of builders liens is that this is a prejudgment remedy that the lien claimant has. That is to say they haven't necessarily proven anything in court, and indeed, they can register their lien through this paper process as soon as they put a shovel in the ground so that they wish.
So to take a quick stock of what we've learned so far, we know that the definition of an owner is wide. We know the definition of a lien claimant is relatively wide. We know now that liens require little paperwork. And so the conclusion you can draw from this is that the possibility for liens is quite wide.
However, it's important not to get bounced. And it's important to get the statement of lien correct because the details are critical. Because the statement of lien crystallizes the lien itself, it can't be amended afterward, and so errors can be fatal.
Common types of errors include naming the wrong land, naming the wrong owner, or in some cases, naming the wrong lien claimant. In each of those cases, there can be fatal to the lien and it can be struck for being invalid. So it's important to get it right. And once more, I'd suggest talk to a lawyer if you're intending to lien or intending to remove a lien. Thank you. Next slide.
JEREMY SAPERS: Thank you, Tom. Again BC has elements in common with Alberta and Ontario. In BC, we do register or submit liens for registration to the land Title office, similar to the land registry office in Ontario. And that's done electronically.
It's a one page form. It's very simple. It can be filled out in PDF or in paper and ink format. And it contains the same information that we heard Tom run through in Alberta. The lien claimant, the owner, the entity who engaged or hired the lien claimant, the amount of the lien, and a short description of the work that the lien claimant performed, or the services or material that they supplied to the improvement.
The form needs to be filled out in the prescribed format with the prescribed information, and if it's not, then the lien can be defected. The land Title office does not scrutinize too closely liens. They'll often register and accept liens that do have defects, and then it's up to the owner or the general contractor, perhaps, to challenge the validity of the lien and bring an application to have it canceled on the basis of those defects.
If the time, the deadline to register lien hasn't expired, then a lien claimant could register. And by doing that, cure a defect in the lien. On the other hand, if the time to register liens has expired and your lien was defective, then the lien claimant has lost their lien rights, likely forever. Next slide, please.
TED BETTS: Now we're going to talk about where the rubber hits the road. I mentioned at the beginning that the lien right is created by statute. It's created from the moment-- the first moment you perform any work or services or provide materials to the improvement.
So your lien right exists throughout the whole course of the project, but it does have an expiry date. It expires by the terms of the statute as well. Aaron mentioned there's a preservation period and to perfection period.
In Ontario, the preservation period is a 60-day lien, what we call the lien period. Before the end of that 60-day period, in order to preserve your lien rights, you must register that claim of lien on Title to the lands on which the improvement is being performed.
That can be done electronically, as Aaron mentioned, or directly by paper at the land registry office. Where it does not attach-- and Aaron talked about when it doesn't attach, usually Crown or municipal lands, public lands, you simply preserve your lien rights by giving the owner a copy of the claim for lien, the crown or the municipality.
That's preserving your lien rights. If you miss that 60 day period, as both Aaron and Jeremy pointed out, as well as Tom, you lose your lien rights. The act requires strict compliance. There's no fixing a missed lean preservation period.
Once you have preserved it, you have another clock that starts ticking, starts a 90-day period to perfect the lien claim. That starts at the end of that first 60-day period. So if you register the lien before the end of the 60-day period, it is still counted from the end of that 60-day period of the lean period.
To perfect your lien claim, you have to actually start an action. Start off formally against the parties to whom you have the lien claim. And then you must register the certificate certificate of action on Title to the property. Now again, if it's a Crown or municipality where the lien does not attach to the premises, all you have to do is commence an action. You don't have a certificate of action to register against Title. Next slide, please.
So just to dig into the time periods a little bit more, so we understand when they start because that's the critical part to it. And for contractors, it's different than for subcontractors. For contractor, again, that's the party that has a direct contract with an owner as defined in the statute.
The 60-day period starts on the publication of the certificate of substantial performance or the date the contract is completed, abandoned, or terminated. We'll go back over these, what is substantial performance in a second.
But the key part there is to recognize that it's not the date of substantial performance. It's not the date substantial performance is certified. It's the date the certificate of substantial performance is actually published. We'll talk about what that means in a moment as well.
The term completed is also a defined term in the statute. So it's essentially when everything on the contract, all the work, all the scope has been completed other than about 1% $5,000. So effectively giving a little bit of a buffer, but not much. It's all done. Once that's done, the clock will start ticking. That does not need a certificate.
Also, if the project is abandoned or if the contract is terminated, the clock will start ticking at that moment. So whichever is earlier of those. Subcontractor has the same two first parts-- the date the publication of certificate of substantial performance is published. That's on the main contract-- on the contractor's contract.
The concept of substantial performance applies to the contractor's contract, not the work done by the subcontractor, or when the prime contractor, the contractor's contract is completed, abandoned, or terminated, the subcontractor's preservation period starts at that point.
They have two additional criteria. And again, this is the earlier of. So the date of last supply of services or materials by the subcontractor will also start the clock ticking, as will the date the subcontract is certified to be complete.
In other words, if you think of a subcontractor, a trade contractor performing work early in the project, their lien rights, their lean period will end far in advance of the completion of the project, and that's an important thing for trade contractors to be aware of.
Again, if you are not preserving on time or if you do not perfect on time, the lien will expire. We'll come back to one exception on that in a moment. But if we can move to the next slide. So I mentioned substantial performance.
Normally, the primary key for defining when your lean period preservation period starts. The focus is on the publication. The publication of the certificate. So the steps you have to go through are you reach substantial completion. Contractor will notify the owner and the architect, the prime architect or the consultant.
They will inspect the work, confirm that it's been substantially performed. And then issue a certificate. Then the contractor will take that and publish it in Ontario. We have three publications in which that certificate can be published to start the clock. Daily Commercial News, Link2Build, or Ontario Construction News. Go to the next slide.
And just as a reminder for those who have heard of it before, maybe haven't looked at the act in a while, when does substantial performance occur? When is the work substantially performed? There are two tests in Ontario. The first is a functionality test. The second is a financial test.
The first test, part A there, is the improvement, the work completed and ready for use? Or is it being used for its intended purposes? So that's one. And two, it's met a financial threshold of the completion of the total contract value.
So roughly, that works out to-- depends on the size of the contract. But there's a mathematical formula. Roughly 97% of the work is done, meaning there's still some work to be done, some cleanup, some defects, maybe to fix up demobilization, some final painting, that kind of thing. But you're basically done. And that's why we start the clock for the lean period at that point in time.
Let's move on to the next slide. So Tom, unfortunately, had to leave to the airport. So I'm going to take over from this point on for Alberta. Although in Alberta, when it comes to the perfection period and the preservation period, we have the same timeline-- 60 days for preserving your lien right and 90 days thereafter for perfecting.
The one exception, not surprisingly for Alberta, is that there is also an oil and gas well or well site work exception for preserving your liens, given the remoteness of the area, they've given you an additional 30 days or 90 days to preserve your lien. For furnishing of concrete as material work done in relation to concrete, the deadline is also 90 days, as opposed to 60 days for preserving your lien. Could move on to BC.
JEREMY SAPERS: Thanks, Ted. In British Columbia, we have a 45-day lien clock. There's no distinction between preservation and perfection. And when the clock starts depends on the circumstances. If a certificate of completion is issued, then the 45-day clock starts on the date that the certificate is issued by a payment certifier.
And in BC, the certification process is a little different than we see in Ontario and in Alberta. It's the constant bugaboo of folks in the construction industry and lawyers. It's unnecessarily complicated. And it's an area that leads to a large number of errors and mistakes.
There's two forms. There is the certificate of substantial completion and then there's a notice of certificate of substantial completion. They both have to be filled out properly. Strict compliance is required. And there's strict timelines as well for when the certificate and the notice both have to be issued. And if there's any errors, again, those certificates or notices can be invalidated.
And that can create a situation where the owner, contractor, or consultant think that the lien clock has expired. But in fact, the clock hasn't even started to run. Another difference is that in British Columbia, the certificates, there's no publication requirement or procedure.
So the certificates and the notice, they have to be posted at a prominent place on the construction site, but there's no public publication of the certificate. And that can create challenges for potential lien claimants who did offsite work like consultants, engineers, and architects, and aren't actually on the improvement plans themselves. They may not know that a certificate has been issued.
The other trigger, if there's been no certificate issued, is 45 days from completion, abandonment, or termination of the head contract. And if there's no head contract, then the 45 days starts to run from the completion or abandonment of the overall improvement or project. Next slide, please.
I'll walk through this quite quickly. It's very similar to what Ted discussed in Ontario. In BC, the act defines completed as substantially performed or substantially completed. And there's the functional and the financial components in BC, as we saw in Ontario. We also have a 3-2-1 formula, although the dollar thresholds are lower than in Ontario. Next slide, please.
TED BETTS: So we mentioned for preservation. We mentioned perfection. I think I've gone through all of this. So just to repeat, after you've preserved it, you've got that 60 days to preserve it. At the end of that 60 days, in Ontario, a second period starts. That's your perfection period.
You have 90 days in which you must issue a statement of claim. That's the formal way. In Ontario, we start a lawsuit. And you must then also issue and register a certificate of action. So that's what gets issued to you when you register the statement of claim, you must register that on Title to the property, unless of course, the lien does not attach to the property. That deadline is unmovable.
But there is one exception for subcontractors. If you have preserved your lien on time and somebody up ahead of you, a subcontractor that you have a contract with or the contractor, the prime contractor, if they have preserved and then they go ahead and perfect their lien claim, there are ways that you can shelter under that perfection, so that you are bringing your claim under their claim in a statement of claim or a cross claim or some other format of commencing an action.
So there is that small exception for sheltering for trade contractors. We can move to the next slide. A lien that is not preserved or perfected on time expires. As I said, it cannot be revived. There is no equity. There is no rule of law that allows the judge to open up that time period. These are strict rights that are strictly set out and only exist because of the statute. And so they must be strictly followed as we keep saying.
Even if you perfect it, though, you've started your action. All the normal rules of law in the province will apply. In Ontario, we have a limitations act that says, if you've commenced an action by issuing a statement of claim, you have to actually set it down for trial within two years. So again, you're still looking at the clock, although you now have time to prepare a proper trial and move on from there.
A discharge lien-- and we'll talk about discharging, vacating lien in a few minutes. But these are different concepts-- discharging or vacating a lien. If it is discharged, it cannot be revived. If it is vacated, it's replaced by money. We'll get into more detail about that technical point in a minute. But if we can move to the next slide.
Alberta is, again, similar to Ontario, although the time period-- if you have preserved and remember we've got-- Alberta, we have 60-day periods for most claims, 90 days for a couple of unique examples in Alberta. After that preservation period, you've got 180 days to actually perfect your lien claim.
And it's done in the same way as Ontario. You must commence an action and the certificate and they call it a certificate of lis pendens is registered on Title. Failure to do either one of those will result in the expiry of your lien rights.
And similar as Jeremy just mentioned about BC, you do have an option to accelerate. If the registered lien holder is served with a written notice to commence action, the lien holder has 30 days to commence an action and register a certificate of lis pendens, failing which the lien will ceasefire to exist.
JEREMY SAPERS: Next slide, please. Returning to British Columbia, this will all sound quite familiar from what we heard in Alberta and Ontario. Within one year of registering a lien in BC, the lien claimant has to do two things. It needs to commence a lawsuit or an action, and they do that by filing what's called a notice of civil claim at a court registry in the province.
And they need to register a certificate of pending litigation that's the same or similar to the lis pendens in Alberta. And that's not a document that's filed at the court. That's a document that's registered on Title at the land Title office.
So when the lien claimant has done those two things, they've perfected their lien, and the following steps will be that the typical litigation court procedure. There is, as Ted mentioned, also an option to accelerate in BC. And it speed things up quite a bit.
It will shorten the time period from one year to 21 days from the delivery of a notice to commence an action. And if the lien claimant doesn't perfect within 21 days, it rolls over onto day 22, then the lien is extinguished and it is gone forever. Next slide, please.
TED BETTS: So I mentioned discharging and vacating. And you can also otherwise remove a lien from Title. So what does that mean? Discharge is a form that is filed by the lien claimant-- so the person who has started this lien.
The lien claimant themselves have decided to remove the lien from Title. That's the only way a discharge actually happens. They file a discharge form and it is removed from Title. Vacate is a common process where any other party can have the lien removed from Title.
And that's important because if lien is there, it's there to protect the claim as it goes forward. And it might be part of a lawsuit. So you would have a lien potentially on Title for years while the lawsuit is being resolved.
That means you are in trouble if you have a mortgage, which probably says you can't allow a lien to stand on your title. It will be a problem if you're trying to sell your property, because no buyer is going to accept the purchase of a property if the lien is still there.
So there is this process by which we can remove the lien but still protect the claim itself. And we call that vacating. And in Ontario, it's done by posting security into court. That security can be in the form of a bond, cash, or a letter of credit.
It covers the full amount of the lien claim, plus an amount of about 25,000 or 250,000, the lesser of, and security for the costs of the claim and the lien and the vacating itself. The lien is then removed from Title and becomes simply a charge on the security. In other words, that security replaces the value of the lien on Title.
There's also the concept of otherwise removed, and that's just a bit of a catch all to reflect the fact a lien on title, and it may be years down the road. Clearly they've not done the next step. They've lost their lien rights, and yet that's still on Title.
Rather than force them to put money into court for something that doesn't have any rights or substance to it anymore, you have a process that recognizes that there are other ways that, that can be removed.
And effectively, that means going into court, proving to them that the lien periods have all expired, no action was commenced. The lien rights are all expired, the court will issue an order and then you have to take the order, go to the land titles office and have the lien removed from Title. Next slide, please.
So Alberta works in a similar way. In section 48, you can pay security into court. Again, it's the same as Ontario, the amount of the claim for lien, also the maximum amount for which lien may properly attach onto the property, that is.
And such lesser amount as the court may determine, plus any costs the court may fix. So it's a little bit of a looser regime and not as prescribed as Ontario. But it works the same way. And an application can be made, just like in Ontario by any party. Doesn't have to be the claimant, doesn't even have to be the contractor. It can be any party. And it can be-- and then the lien is removed from Title and becomes simply a charge on the security that's put into court. Jeremy.
JEREMY SAPERS: Thank you, Ted. Similar story in British Columbia, liens can be discharged or vacated upon the posting of sufficient security. Like in Ontario, that security can take a few different forms. It can be cash, a bond, or a letter of credit.
Often a bond is preferable by owners or general contractors if they don't have sufficient cash flow to secure the lien itself in cash. And the way a bond works is it's underwritten and issued by a surety, and the party that took out the bond will typically pay monthly premiums on the bond that usually are a percentage of the value of the bond or the lien itself.
So the immediate cash outflow for a bond is typically much lower than securing a lien with cash. The value of the security is usually the full face value of the lien, and British Columbia is different than Ontario. And in Alberta, the security will not include any allowance for costs. So it is only the face value of the lien that needs to be secured.
And as in the other provinces, in British Columbia, this can be done by court application, although these are routinely done by consent. So if the parties are all acting reasonable, they are represented by counsel who are familiar with the procedure.
An application is usually not necessary, and the parties can negotiate the terms of a consent order. And from start to finish, if everyone is focused on the project, a lien can be removed, typically within a few days. If an application is necessary, then the procedure can take longer than that. Next slide, please. Aaron you're up.
AARON HUNTER: OK. It is me again. Holdback, holdback in Ontario. So the topic of holdback goes hand-in-hand with the topic of liens.
We often discuss them together. The key concept for those of you who aren't already familiar with holdback and working with it is if you hire someone to do work for you on a construction project, and it's the kind of work that gives rise to lien rights under the statute in Ontario or whatever other province, then you must apply holdback when you're paying that person.
And what do I mean by apply holdback? Specifically, it means that when you get an invoice from that person or that firm that's doing the lienable work, you can only pay 90% of that invoice. You have to at least notionally hold back the remaining 10%.
And the point of this is to create a pool of money to protect subcontractors of all tiers who are in a vulnerable situation in terms of the certainty of getting paid and who are at heightened risk of not getting paid.
So the holdback is not, as some people think, meant to be used to fix things that the contractor or subcontractor didn't do properly. It's for protecting the people who are a couple of notches down the pyramid or a couple of rungs down the ladder.
And, as you may have already gathered, it doesn't just apply to the prime contractor, the top of the pyramid between the owner and the contractor. It applies all the way down the ladder or pyramid. So, for example, if there's a subcontractor 3 rungs down, and it has its own subcontractor, when it gets the invoice from its subcontractor, it can only pay 90% of that invoice.
So it goes all the way down. And quickly-- sort of beyond the scope of the presentation to talk about release of holdback in too much detail. But quickly, under the Ontario Construction Act, as amended, there are two or three different ways that holdback can be lawfully released.
There's a new process for annual release of holdback, which is driven by the owner, and it's initiated on the anniversary of a contract that you enter into. And the owner is responsible for driving it. Then there is also release of holdback at the end of the contract, after substantial performance has been achieved and all lien rights have expired.
And the one that's not mentioned on this slide, but I'll mention it briefly, is if you have a long project and a subcontractor completes its work in the middle of the project and wants to get its hold back, there is a mechanism in the Construction Act for getting the holdback that applies to that specific contractor to them-- from the owner, through the prime contractor to that subcontractor. So I will leave it there and ask Ted, I think, to speak to holdback in Alberta.
TED BETTS: Great. Thank you. So Alberta, holdback works in a similar way, except there's one unique aspect to it that we talk about-- so it is a 10% in Alberta as well. But we talk about the major lien fund and the minor lien fund in Alberta.
Major lien fund is the holdback that is retained up until substantial performance, and then the minor lien fund, there's a second fund that is created, the 10% of the value of the work that's performed after substantial performance.
Otherwise, it's basically the same as Ontario. Holdback is retained for the benefit of the lien holder. And the owner can pay the holdback out at any time to discharge all liens and free itself of further liability. Jeremy.
JEREMY SAPERS: Thank you. In British Columbia as well, the holdback is 10% of the price or the value of the work, and it's typically retained from each progress payment, as Aaron described happens in Ontario. It's intended to serve two primary functions.
The first is to protect or secure payment to subcontractors. And the second is the point that Ted finished off with in Alberta, which is that the holdback can operate as a limitation of liability for owners. If they've properly maintained the holdback account and it has the correct amount of funding in the holdback, then the owner can pay the hold back in and clear themselves of any liability to subcontractor lien claims.
In terms of the release of a holdback, it operates similar to Ontario, as Aaron walked through. The holdback can be released upon the issuance of a certificate of substantial completion for a contract or a subcontract, or upon substantial completion of the head contract or the improvement.
One difference to note, Aaron mentioned that the net to hold back in Ontario isn't used as a fund to cover the cost of deficiencies or defects in the work. In British Columbia, if the holdback period has expired or if the owner is in a position to release the holdback, and there haven't been any lien claims registered, at that point in time, the owner can assert a set of against the holdback funds for any damages that they've incurred.
So that can be the cost of correcting defective work. That can be damages incurred for delay. So at that point in the process, the owner can claim set off against the holdback fund. Next slide, please.
TED BETTS: We're going to talk about another very powerful remedy and protection that's in the Construction Act. We talked about liens. We know that liens exist by statute and they can expire. We talked about holdback, and how that gets paid out.
Trust claims, often more powerful than any of the other remedies that are in the statute. That's because it gets right to the heart of the payment. Again, it exists only because the statute-- it creates what we call a construction trust for any payment that is received, that is owed to somebody else on the project, there is a construction trust on that.
So if the owner receives money from a lender or sets money aside dedicated to the project and do a project bank account, the trust automatically triggers and that money can only be used to pay down to the contractor.
Similarly, a contractor and a subcontractor, everybody down the chain who receives money that is owed to somebody else on the project, a trust is created over those funds. And then there's a vendor's trust that also applies to an owner on sale. Next slide, please.
So what does that mean? Trust law goes back hundreds of years in the common law. And it creates a powerful obligation to deal with the trust property, which in this case is money very carefully and properly. The statute actually goes further and says a couple of things. One, it imposes requirements to treat that money in a segregated account.
In Ontario, that does not necessarily mean that you have to take any funds and put it into a separate bank account, but you do have to account for it. You do have to keep separate books and records for that fund, separate from other projects that you might be working on or your general company bank account, so that we can trace the funds that are coming through the system and that might be owed down the construction pyramid to others.
You cannot use those funds for any other purpose than to pay the party that it's owed to on the project. This is where parties have, in the past, gotten into a lot of trouble. They take the money, they are on one project. They're a little behind on another, and they apply it to that other project. You have breached the trust obligations the moment you've done that.
What that means is not just that you don't have the money. And if we could go to the next slide, and here's the power of the trust that why most people would say it's even more powerful, the people who made the decisions to make that payment that's counter to the act, that breaches the trust, they can be personally liable.
So if you as a project manager, take funds from one project, go and pay somebody else, and you never have the money to pay your contractors below you, you as a decision maker, having taken that money and done that, your officers, directors, and you personally can be liable for that.
The money for one project has to stay on one project. It gets around contract law, it gets around the onus of proof, gets around much of the bankruptcy and insolvency. If it could go to the next slide. We have to be cautious about bankruptcy/insolvency laws.
The strict rules are there because we want to ensure that a company doesn't go bankrupt without any money, and that the money that's been paid into the project stays in the project. But federal paramountcy constitutional rules will still apply to whatever money is there.
And so there are protections, and it goes further than the rest of the statute when it comes to federal bankruptcy and insolvency act and other insolvency rules. But for the most part, it's that additional protection. Next slide, please.
Alberta, trust provisions are very similar but much weaker because they only apply after the date of certificate of substantial performance is issued. So in other words, it's only available to protect those payments to keep them within the project until the very end of the project. So it's quite a bit weaker and doesn't have the same strength as it does in Ontario. Jeremy.
JEREMY SAPERS: BC looks much like Ontario and less like Alberta. There's robust trust protections that are set out in the BC Builders Lien Act. I won't go through the policy and the remedies that Ted explained. They all apply equally in British Columbia.
I will highlight two notes that the Builders Lien Act in BC creates two statutory trusts. So any funds that are held in a holdback account, they're impressed with a trust. So they are trust funds. And similarly to what Ted described, any money that is received by any party up and down the contractual pyramid chain of contracts, those are trust funds held for the benefit of the parties below them.
So if the owner pays the general contractor, the general contractor receives that payment in trust. And the beneficiaries of the trust are the subcontractors. And those funds have to be used to pay the subcontractors first before the funds are used for any other purpose. Next slide.
AARON HUNTER: Thanks, Jeremy. OK, back to Ontario. Ontario has had what we call prompt payment in our construction legislation for a few years. What does it mean for those of you who aren't already familiar with it? It means, essentially, that an owner can't force a contractor and a contractor can't force a subcontractor to accept really unreasonable payment terms.
For example, you can't make them wait 60, 90, or 120 days to get paid. You can't insist on a strict pay when paid approach. Anything that you put in your contract about payment terms and timing, to the extent that it contradicts the Construction Act, the Construction Act is going to override it.
So let me describe the basic idea. Basic idea is everything starts with the owner's receipt of a proper invoice. That is a defined term in the Construction Act. And when the owner receives a proper invoice from the contractor, that starts the clock, and the clock runs for 28 days, and that invoice needs to be paid by the 28th day.
There are some nuances to this, of course, and we'll talk about those in a minute. But that's the basic idea. The proper invoice and the 28 days. Once the contractor has received payment within the 28-day period. It then has seven days to turn around and pay its subcontractors.
And then that same pattern of the seven days continues on down until the bottom of the ladder, or bottom of the pyramid of subcontractors, regardless of how many tiers there are. Next slide, please.
So as I mentioned, the proper invoice is defined in the Construction Act. And it's a big laundry list of things, information that has to go in the invoice for it to constitute a proper invoice. I know that what I've got up here on the slide is too small for people to read. I just wanted to give you the sense that it's a big list of things, and a proper invoice is a core concept for understanding prompt payment in Ontario to build on. Next slide, please.
So most of the requirements for a proper invoice are pretty common sense and unsurprising. They're just what you'd expect. I mean, your invoice needs to say what the amount payable is. No shocker. And there should be a description of the goods or services provided, et cetera, et cetera-- a lot of common sense things.
But I do want to note some things that are-- if not surprising, then at least important to note. The contract that you have as between the owner and the contractor or between the contractor or subcontractor, it can spell out additional things that have to go into a proper invoice.
So let's say, for example, the contract says the proper invoice has to include all of the Construction Act stuff on that list, it also must include the contractor's HST number. Well, then it becomes part of the definition of proper invoice.
And if the contractor submits an invoice that doesn't have the HST number, it was required by the contract to include it, then it's not a proper invoice in the clock-- that 28-day clock I was mentioning does not start.
Another point I'd like to make is that proper invoices by default are supposed to be issued once a month in the expectation that your billing for services performed in the previous month. But we all know that some contracts don't work like that. Some are based on milestone, have a milestone payment structure, and the new Construction Act in Ontario, as amended this year contemplates milestone payment structures.
So if you have one of those structures, you have to say in the invoice we achieved this milestone. That's why we're invoicing this amount at this time. And finally, another recent addition to the definition of proper invoice is the last bullet here on the slide, any other information necessary for proper functioning of the owner's AP system that the owner requests.
So if the owner says, listen, I need you to include a certain code in your invoices at the top and the contractor refuses, then it's not going to count as a proper invoice. And even if you send it to the owner, the clock won't start. Next slide.
So as mentioned, after receipt of a proper invoice, owner has 28 days to pay. But there are things that can happen. The first thing I want to mention, and I guess it's repeat is that it does have to check all the boxes to count as a proper invoice or the clock won't start.
And as an owner, you can't wait until day 27 to raise an issue and say, oh, this invoice is deficient or defective because it doesn't include this, this, and this item that are required for a proper invoice.
Under the latest amendments to the Construction Act, there's a requirement for you as an owner who receives an invoice to speak up within seven days and say the invoice is missing this, this, and this. Otherwise, after seven days, it's going to be deemed a proper invoice and the clock will be deemed to have already been running for seven days. So it prevents some sort of gaming and manipulation of the system.
Also, moving down the slide, as you'd expect, if there are problems with the work itself, then the owner has 14 days from receipt of the proper invoice to give notice to the contractor that, listen, we're short paying because there's a problem with this aspect of the work or this is missing or this was not done properly.
And those notices have to be in a certain form, as set out in the Construction Act. And among other things, they have to specify the amount of the dispute, the amount in dispute, what's going to be short paid and set out the reasons. And even if you do give the contractor a notice of non-payment, at the end of the 28-day period, you are obliged to pay whatever amount was undisputed. Next slide.
So how does it work when you go down the ladder or go down the levels of the pyramid? Once a contractor receives payment from the owner, the money is starting to flow down the pyramid. And there are rules for that too, for the timing of it.
The contractor has to turn around and pay its first layer of subs, its direct subcontractors within seven days of receiving payment from the owner. Similar to the owner's rights, the contractor can say there's a problem with the work. I'm going to pay only part of the invoice or none of the invoice.
And similar to the owner, the contractor in that situation needs to issue a notice of nonpayment and include reasons and pay whatever the undisputed portion is. Of course, if the owner doesn't pay the contractor, that creates a problem for the contractor.
And you might be asking yourself, oh, so is there a pay when paid situation? I mean, if the contractor doesn't get any money, what does it have to do? Well, under the Construction Act, it's not a straightforward pay when paid-- it's really important to note that.
The contractor does need to pay the subcontractor regardless by the 35th day, unless the contractor has taken steps to make a claim against the owner by initiating what's called an adjudication.
So can you go to the next slide, please? It's got a bit ahead of myself there. So if the owner doesn't pay the contractor, the default situation is it still must pay the subcontractor by the 35th day, unless the contractor has stepped up and initiated an adjudication against the owner to get things moving and encourage the payment to start flowing down.
Some of you probably know adjudication is fast track, simplified dispute resolution process that was created by the Construction Act and that parties can use instead of going to court or before going to court to save time and money.
So contractor cannot just say, sorry guys, we didn't get paid. Therefore, you're not going to get paid. It's a more nuanced situation than that. I have one more slide. Next slide, please. Remedies for non-payment.
I mean, the most important remedies for non-payment are the ones that exist in your contract, whatever that says. And of course, you can sue for breach of contract or terminate or suspend or whatever other remedies you have available to you under the contract.
But the Construction Act does offer some extra remedies. In this situation, statutory interest will accrue on the amount owing. And there are under some circumstances, suspension rights. But really it's your contract that you would probably look to first for the remedy for non-payment and liens. So with that, I will turn it over to Ted for prompt payment in Alberta.
TED BETTS: Yeah. Just very quickly, it is the same. Alberta looked at what Ontario did and brought in prompt payment and adjudication rules in 2022. Initially, it was a little bit different and then after getting public feedback, especially from the contractors, it adjusted.
So it is almost virtually identical to the Ontario regime that Aaron just described, including the obligation to pay-- if you go to the next slide, within 28 days of a proper invoice, and then for contractors to pay within seven days.
But if an owner does not pay, contractors still must pay, or they have to start enforcing their rights by starting an adjudication. If there's a dispute on the amounts claimed in a proper invoice, like in Ontario, there are specified statutory forms that need to be prepared and issued. But otherwise, it's exactly the same as Ontario. And BC is different. Coming soon.
AARON HUNTER: Thanks, Ted. Yeah BC is still behind the times. Unfortunately, we've had a few false starts in having prompt payment legislation implemented here. It is coming. The prompt payment legislation received royal assent in November, the end of November of last year, and the province has been in consultations with the construction industry really since then. And a more intense phase of discussion started in July.
We really did think that it was imminent. And then our premier EB called a snap election for the end of this month. So that will likely delay the introduction of this legislation. Once it is finalized and the regulations or the legislation, part of me, is in its final form and the regulations are released, we'll be delivering a number of webinars to explain that legislation and how it impacts projects in British Columbia. So stay tuned for that. And I think I'm now handing the floor back over to Jessica.
JESSICA FOSTER: Perfect. Thank you so much, Jeremy, and as well to Ted, Aaron, and Tom for walking us through these concepts. We do have a question that just came in and we have a couple minutes left. So I think this one is going to be for Aaron as it involves Ontario's Construction Act.
The question is, what is the timeline for a notice of nonpayment to be issued from a contractor to a subcontractor? And the section that is referenced in section 6.4 sub 2 of the Construction Act-- the exception notice of non-payment if dispute. So really putting you on the spot there, Aaron.
AARON HUNTER: That's OK. So my understanding is the contractor is meant to pay within seven days of getting paid by the owner. And if the contractor wants to issue a notice of non-payment, it has to issue that notice within that seven same day period. And I'm looking at Ted to see if he is on the same page as me with that, that it's seven days.
TED BETTS: And then the same with necessary modifications down the chain from contractor to subcontractor, subcontractor to sub.
JESSICA FOSTER: OK, wonderful. Well, that is perfect timing. So we will wrap up there. A big thank you again to everyone in the audience for joining us today. And as has popped up on the screen, please do take the time to complete our survey. And we look forward to hopefully seeing you at our next session on environmental liability insurance and bonding on October 27. Thank you again. Have a great one.
[AUDIO LOGO]
You can download a copy of the
presentation here.
Join Gowling WLG and Aon for the next installment of our seven-part webinar series designed to help construction and infrastructure stakeholders navigate an increasingly complex project landscape. Whether you are an owner, contractor, consultant, or insurance or risk management professional, this session will provide practical insights to support informed decision-making throughout the project lifecycle.
We will explore key considerations related to construction liens and payment requirements across Ontario, Alberta, and British Columbia. Topics will include:
This program is eligible for up to 1.5 hours of substantive CPD credits with the LSO, the LSBC and the Barreau du Québec.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.
Gowling WLG is an international law firm comprising the members of Gowling WLG International Limited, an English Company Limited by Guarantee, and their respective affiliates. Each member and affiliate is an autonomous and independent entity. Gowling WLG International Limited promotes, facilitates and co-ordinates the activities of its members but does not itself provide services to clients. Our structure is explained in more detail on our Legal Information page.
© 2026 Gowling WLG All rights reserved.