A recent decision of the Technology and Construction Court (TCC) provides important guidance on the intersection of the new building safety regulatory regime and the Court's case management powers in high-value construction disputes.
In GS Woodland Court GP 1 Ltd & Anor v RGCM Ltd & Ors [2026], the TCC considered the case management consequences of the Building Safety Regulator (BSR) rejecting a claimant's proposed remedial scheme for a Higher Risk Building (HRB).
This case is significant: it is one of the first TCC judgments to grapple directly with the case management implications of BSR delays. It makes clear that the BSR's decision on a remedial scheme is a factual matter that may materially influence how a court manages proceedings, particularly in relation to quantum. For parties procuring remedial works to HRBs, this illustrates the risk that BSR delays or adverse decisions can derail even well-advanced litigation timetables.
Below we examine how the dispute arose, the parties' arguments, and how the TCC reached its decision.
The TCC held that the "least imperfect" option was to order a split trial: rather than adjourning the entirety of the proceedings, the June 2026 trial date would be retained for the determination of liability issues, with quantum to be heard separately at a later date.
Mr Justice Constable acknowledged that, in a typical construction defects case where remedial works have not yet been commenced, the court will ordinarily rely on expert evidence to determine what remedial works are reasonably necessary and their cost. There is an inherent degree of uncertainty in any such exercise: the scheme ultimately carried out may cost more or less than that assessed by the court, and the claimant bears the risk of subsequent regulatory changes or delay. Ordinarily this uncertainty would not be sufficient to affect a case management decision about when the trial should be heard.
However, the Building Safety Act 2022 and the Building (Higher Risk Procedures) Regulations 2023 introduced a qualitatively different consideration. Because the Development was an HRB, it was unlawful to commence any remedial works without BSR approval. Following the BSR's rejection, the "one certainty" was that Woodland was not legally permitted to carry out its pleaded remedial scheme. This was not merely a risk of future non-approval materialising after trial — which the judge accepted was a risk any claimant bears — but an established fact that the proposed scheme could not, as matters stood, be implemented.
Ultimately, the judge concluded that it would be unfair to require Woodland to proceed to trial on quantum in circumstances where the situation had arisen through no fault of Woodland's own. Applying the guiding principle from Bilta UK Limited v Tradition Financial Services Limited [2021] — that the assessment of fairness is fact-sensitive and not to be judged by mechanistic application of any checklist — he held that an adjournment of the quantum issues was necessary to afford Woodland the opportunity to regroup and re-plead its losses.
If you have any questions about this article, please get in touch with Jessica Tresham or Emma Knight.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.
Gowling WLG is an international law firm comprising the members of Gowling WLG International Limited, an English Company Limited by Guarantee, and their respective affiliates. Each member and affiliate is an autonomous and independent entity. Gowling WLG International Limited promotes, facilitates and co-ordinates the activities of its members but does not itself provide services to clients. Our structure is explained in more detail on our Legal Information page.
© 2026 Gowling WLG All rights reserved.