Sahil Shoor
Associé
Article
10
A recent decision from the Ontario Superior Court of Justice serves as a useful reminder to construction companies on the importance of contractual language — especially when it comes to payment contingent on third-party certificates.
Pentad Construction Inc. v. 2022988 Ontario Inc.[1] centred on an invoice dispute between a sub-contractor ("Pentad") and the project manager of a residential development ("Armor"). The former was retained by the latter for site preparation, importing clean fill, grading, stormwater management, underground services, and primary, boundary and secondary roadways.
During the course of the contract, a dispute arose with regard to outstanding payments and the value of work completed by Pentad.
Importantly, the contract between Pentad and Armor stipulated that "[Pentad's] work performed/provided under [the] Contract shall be inspected for quality and quantity and certified complete, received and approved by [Armor's] authorized Engineer, prior to any sums becoming due hereunder."[2]
Pentad grew frustrated with the failure of Armor's authorized Engineer to certify claims for payment. The authorized Engineer's certificates, in fact, indicated that Pentad had been overpaid during the course of the contract.[3]
As a consequence of opposing views, Pentad halted work and registered a lien in under the Construction Act (Ontario) (the "Act") for the amount of $479,364.57.
Armor, in turn, brought a motion asking the court to reduce the amount of security it posted to bond off Pentad's lien to zero. It relied on s. 44(5) of the Act, which provides:
(5) Where an amount has been paid into court or security has been posted with the court under this section, the court, upon notice to such persons as it may require, may order where it is appropriate to do so,
(a) The reduction of the amount paid into court, and the payment of any part of the amount paid into court to the person entitled; or
(b) The reduction of the amount of security posted with the court, and the delivery up of the security posted with the court for cancellation or substitution, as the case may be.[4]
Pentad argued that s. 44(5) of the Act is meant for simple matters and not complex factual disputes, which are best resolved at trial. Indeed, Pentad suggested that it and Armor were in disagreement over key facts, including (1) the identity of the authorized Engineer and (2) whether or not they carried out their responsibilities as payment certifier in good faith and in compliance with the terms of the contract. Thus, it sought the dismissal of Armor's motion.
On the other hand, Armor stressed the simplicity of the motion's key issue: were the decisions of the authorized Engineer binding? If so, the basis for Pentad's claim was lost.
In support of that position, Armor argued that (1) it and Pentad agreed, pursuant to the aforementioned clause, that payment would be made only after Pentad's work was certified by the authorized Engineer, whose decision would be final and binding absent demonstrated fraud or bad faith; (2) it was clear at all times that the parties knew who was the authorized Engineer; (3) the amounts claimed by Pentad were not certified by the authorized Engineer; and (4) Pentad had not advanced an assertion or evidence of bad faith, fraud or willful disregard of duty on the part of the authorized Engineer.
Justice Boswell found merit in Pentad's position that the Act is not intended for time-consuming interlocutory motions, but he was ultimately satisfied that the issue at the core of the motion — "the determination of whether Pentad is bound by the decisions of the payment certifier" — could be determined in a summary way.[5]
In his analysis, Justice Boswell relied on Federated Contractors Inc.[6], in which Justice McKinnon canvassed 150 years of jurisprudence supporting the thrust of Armor's position: Armor and Pentad agreed to a payment certification provision and are bound by the decisions of the third-party certifier. That is, the law holds that "where payments are dependent on certification — the determination of the payment certifier is final and binding, absent fraud or bad faith, or a knowing and wilful disregard of duty."[7] Justin McKinnon noted this principle is the case because, as summarized by Justice Boswell:
Justice Boswell also turned to leading case law on contractual interpretation, citing Sattva Capital Corp. and Ventas, Inc., and noted that the interpretation of a commercial contracts are to be "grounded in the text and read in light of the entire contract" and that the "cardinal presumption is that the parties meant what they said."[9] Thus, the terms of an agreement govern — and to that end, courts will enforce a binding provision that parties have agreed to "as long as the payment certifier acts fairly, honestly and impartially and provided there is no collusion between the owner and the certifier."[10] Contractual terms stipulating that payment certifications are non-binding or "provisional" will not be enforced.[11]
It was clear, according to Justice Boswell, that Armor and Pentad intended, as per the agreement, to be bound by the determination of the authorized Engineer, and such would be enforced absent the third-party's fraud or bad faith, or their knowing and willful disregard of duty.
Pentad Construction Inc. v. 2022988 Ontario Inc. offers important considerations for companies involved in the construction pyramid.
First, contractual interpretation continues to be "grounded in the text and read in light of the entire contract." Second, courts presume that parties have meant to be bound by their bargain — and so, what parties agree to is key. Finally, the decisions of third-party payment certifiers, made in the context of a contractual provision stipulating that such decisions are binding, will be enforced absent fraud or bad faith, or a knowing and wilful disregard of duty. Companies must be attentive to such contractual language and whether there is a transparent and clear process for certifier decisions or room to challenge such decisions.
Should you have any specific questions about this article or would like to discuss it further, you can contact the authors or a member of our Infrastructure and Construction Group.
[1] Pentad Construction Inc. v. 2022988 Ontario Inc., 2021 ONSC 824 [Pentad].
[2] Ibid at para 16.
[3] Ibid at para 57.
[4] Construction Act, R.S.O. 1990, c. C.30, s. 44(5).
[5] Ibid at para 88.
[6] Federated Contractors Inc. v. Ontario (Management Board of Cabinet), 2007 CanLII 3218, [2007] OJ No. 463 (ONSC) [Federated].
[7] Pentad at para 99, citing Federated.
[8] Pentad at para 92, citing Federated at 46-49.
[9] Pentad at para 97, citing Sattva Capital Corp. v. Creston Moly Corp., 2014 SCC 53 at para 57, and Ventas, Inc. v. Sunrise Senior Living Real Estate Investment Trust, 2007 ONCA 205 at para 24.
[10] Pentad at para 93.
[11] Ibid at para 93-94.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.