Gus Wood
Partner
Co-leader of Energy (UK)
Article
The National Energy System Operator (NESO) has announced an updated timeline to Great Britain’s grid connections process, aiming to fast-track shovel-ready clean energy projects and unlock up to £40 billion in annual economic growth.
This marks a significant departure from the traditional first-come, first-served model, reflecting a broader commitment to strategic planning and delivery certainty. The move is expected to reduce delays and improve transparency for developers navigating the grid connections process.
In this article, we explore the implications of NESO’s newly announced grid connections reforms, outlining how the changes may reshape project delivery timelines and strategic planning across the UK energy sector.
NESO’s roadmap, developed in collaboration with the UK Government, Ofgem, and distribution network operators, introduces a restructured queue system that prioritises projects ready for delivery in 2026 and 2027. Revised connection offers will begin rolling out in December 2025, with longer-term projects addressed in the following year.
This reform responds to longstanding industry frustrations over grid bottlenecks and opaque connections timelines. NESO’s admission that its evidence submission portal had hindered progress underscores the need for legal clarity and procedural transparency.
The acceleration of grid connections timelines is likely to have a ripple effect across associated planning and environmental processes. Projects with compressed delivery schedules may attract closer attention from local authorities and statutory consultees, particularly where infrastructure intersects with sensitive land use or regulatory thresholds.
As the new prioritisation framework takes shape, questions around procedural fairness and transparency may emerge especially from stakeholders whose projects are repositioned in the queue. Observing how NESO implements its roadmap in practice will be key to understanding the broader implications for governance, stakeholder engagement, and long-term infrastructure planning.
NESO’s grid reform represents a bold step toward achieving the UK’s 2030 clean power target. By introducing a more dynamic and readiness-based framework for infrastructure delivery, the roadmap encourages early engagement, strategic alignment, and greater delivery certainty. As the energy sector adapts, success will depend on proactive planning and a clear understanding of evolving regulatory priorities.
If your organisation is navigating the implications of NESO’s grid reform or preparing for upcoming changes to project delivery timelines, our Energy team is here to help. Please contact Gus Wood, James Stanier or George Nixon.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.