Sean Adams
Partner
Commercial Disputes, Chair of the Nordic desk
Article
8
If a breach of contract is repudiatory in nature, can that breach ever be remedied, or is it automatically irremediable? The Court of Appeal recently considered this and related questions in its judgment in Kulkarni v Gwent Holdings Ltd & Anor [2025] EWCA Civ 1206. In this article we outline key aspects of the judgment and highlight practical considerations for parties assessing termination rights, remedies and next steps when a breach arises.
Where one party is in breach of contract, the innocent party may have various options:
The dispute arose in the context of a shareholders agreement (SHA) concerning the operation of an independent hospital. There were two initial shareholders in the hospital operating company – Mr Kulkarni, and Gwent Holdings.
Under the SHA, certain events would trigger a process for the compulsory transfer of a shareholder's shares. One of those trigger events was "the Shareholder committing a material or persistent breach of [the SHA] which, if capable of remedy, has not been so remedied within 10 Business Days of notice to remedy the breach being served…"
Following disagreements between the shareholders about operation of the hospital, Mr Kulkarni brought proceedings alleging that Gwent had committed various material breaches of the SHA, and that those breaches had triggered the provisions in the SHA for compulsory transfer of Gwent's shareholding.
By the time of the trial, Gwent admitted three of the alleged breaches of the SHA. It also admitted that these breaches were 'material' within the meaning of the SHA, and that two of them were repudiatory in nature. At trial, the judge found that there were four 'persistent' and 'material' breaches within the meaning of the SHA – but concluded that all four breaches (a) were remediable and (b) had in fact been remedied - meaning that Mr Kulkarni was not entitled to compel Gwent to transfer its shares. Mr Kulkarni appealed.
The main issues in the appeal were as follows:
The compulsory transfer clause in the SHA contained cure wording – "a material or persistent breach of [the SHA] which, if capable of remedy, has not been so remedied within 10 Business Days of notice to remedy the breach being served."
At first instance the judge held that, on a proper interpretation of this clause, in the event of a breach that was capable of remedy, the share transfer process was not triggered until the 10-day cure period had elapsed. Since no notice to remedy had ever been served in this case, the transfer process was not engaged.
On appeal, Mr Kulkarni argued that remediation was only relevant if a notice to remedy was actually served. If no notice to remedy was served, then any material or persistent breach triggered the transfer clause, regardless of whether the breach was remediable (or in fact remedied).
The Court of Appeal upheld the judge's decision – on a proper construction of the SHA, a shareholder could not trigger the compulsory transfer process on the strength of a remediable breach without serving a remedy notice.
This led the court to the second issue under consideration – whether a breach which is repudiatory in nature can ever be remediable.
Under this issue, the court considered the interaction between the common law right to terminate for repudiatory breach, and alternative contractual rights that may arise from the same breach. At first instance, the judge made clear that while the breaches were repudiatory in nature (i.e. they could have given a right to terminate at common law), that did not necessarily mean they could not be remedied within the meaning of the SHA.
Mr Kulkarni argued on appeal that a repudiatory breach of the SHA could never be capable of remedy, and so there was no need to serve a notice to remedy.
Citing a number of authorities drawn from different sectors, the Court of Appeal agreed with the judge that "[t]he fact that certain of the breaches of the SHA were repudiatory in nature … did not, in itself, render them irremediable for the purposes of clause 7.1(d)".
The court went on to say that, when determining if a breach of contract is remediable, the court will usually apply "a practical rather than technical approach" in which common law rules of repudiation have no place. The key question is whether the mischief caused by the breach can be removed, to put matters right for the future. For example, drawing on previous authorities:
Applying that "practical not technical" test, the Court of Appeal held the judge in this case was entitled (and right) to find that Gwent's various breaches of the SHA were capable of remedy:
While this judgment revolved around a shareholders' agreement, the principles considered by the Court of Appeal may have potential application in a much wider range of scenarios - for example when exercising termination rights for material breach in commercial contracts. Key considerations for those operating any such contracts can be summarised as follows:
Need clarity on whether a breach of contract is repudiatory, remediable, or both? Our contract disputes specialists can help you assess termination rights, decide when (and how) to serve a cure notice, and draft clauses that reduce ambiguity around remedy vs. repudiation in shareholders' and wider commercial contracts. If you're currently facing an issue or want to stress‑test your agreements, get in touch Sean Adams or Catherine Naylor for bespoke expert advice.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.