Michelle Cicchino
Associate
Article
11
Originally published on April 1, 2020
Last updated May 26, 2020
The Province of Ontario, municipalities and affected Boards and corporations are in the midst of dealing with emergency processes to aid property tax payees throughout Ontario in response to the COVID-19 outbreak.
The end of March is typically the deadline for appeals to the Assessment Review Board for each taxation year for most property types. In addition to appeals, based on Ontario's four-year assessment cycle, the assessment of all properties was scheduled to be released starting in Spring 2020. This assessment sets the value upon which taxes are based for the following tax assessment cycle (typically for four years).
In an unprecedented move, the Government of Ontario's passing of O. Reg. 73/20 has changed both appeal deadlines for the 2020 taxation year and the assessment cycle for the 2021 taxation year.
If your property falls within the residential, farm or managed forests property class, an appeal cannot be filed with the Assessment Review Board unless a Request for Reconsideration ("RfR") has been made with the Municipal Property Assessment Corporation ("MPAC"). Other properties within Ontario may also file an RfR prior to filing an appeal, though this step is not required. The RfR deadline is usually March 31 of the applicable taxation year.
Pursuant to O. Reg. 73/20 under the Emergency Management and Civil Protection Act, MPAC has stated that the deadlines to file certain RfRs may have been extended. Property owners can log into AboutMyProperty to learn their new deadline for submitting an RfR.
On March 26, 2020, the Assessment Review Board acknowledged that O. Reg. 73/20 suspended limitation periods and procedural time periods retroactive to March 16, 2020. The Assessment Review Board has not addressed how O. Reg. 73/20 impacts appeal deadlines.
The Assessment Review Board, as of May 11, 2020, is permitting appeals to be filed by May 29, 2020.
Property taxation is based on the assessed value of properties and in Ontario those assessments are updated every four years. The last assessment update was in 2016 (the "2016 Current Value Assessment (CVA)"), with the Ontario government planning on completing the Ontario-wide reassessment in 2020 for the 2021 taxation year. This would have meant new assessments being issued beginning this Spring 2020.
Pursuant to O. Reg. 186/20, amending O. Reg. 282/98, the 2021 taxation year will be based on a January 1, 2016 valuation date. This means that existing appeals will include a deemed appeal for an additional year if they are not resolved by 2021. This change should assist in helping resolve the pre-existing backlog of municipal tax assessment appeals in Ontario.
The Government of Ontario has deferred the quarterly remittance of education property tax to school boards by 90 days with the hopes that municipalities would be able to pass on property tax deferrals to their constituents. Many municipalities have created a property tax relief deferral program to aid its constituents during these times. For municipalities not listed below, please reach out to your municipality or Gowling WLG to find out what options are available for your property.
The City of Ottawa provided a grace period for payment of interim taxes to Wednesday, April 15, 2020.
The City of Ottawa also created an interest free 30-day payment grace period for all unpaid water bills issued before April 1, 2020, and a 30-day due date extension for all water bills issued between April 1, 2020 and October 30, 2020.
2020 Property Tax Hardship Deferral Program
On March 25, 2020, the City of Ottawa created the 2020 Property Tax Hardship Deferral Program for both residents and businesses that have an assessed property value of up to $7.5 million. Property owners must apply before July 31, 2020. To qualify for the program, the applicant would need to demonstrate the following:
The applicant will not qualify for the 2020 Property Tax Hardship Deferral Program if any of the following apply or occur:
Qualified applicants will have both their interim 2020 taxes and final 2020 taxes deferred to October 30, 2020.
The City of Toronto provided a 60-day grace period for property tax payments and payment penalties from March 16, 2020 for all customers, which ended on May 15, 2020. The City of Toronto utility bill relief also ended on May 15, 2020.
Toronto City Council intends to vote on May 28, 2020 on a proposed property tax payment deferral program. The program would permit impacted residential and business property owners with no other financial options to use an online application process to request additional time to pay their taxes without incurring late payment policies or interest charges during the six month period between June 1, 2020 to November 30, 2020. If passed without amendments, applicants would have to meet the following criteria:
The City of Waterloo is in the process of developing an application-based property tax deferral program to extend 2020 final property tax due dates by 60 days for residents and businesses who qualify. Requirements to qualify for the program have not yet been determined.
The City of Waterloo will continue to waive penalty and interest on property taxes for the month of June 2020. The City of Waterloo will also waive late payment charges on utility bills and miscellaneous receivable invoices for the month of June 2020.
All collection efforts have been suspended until August 31, 2020, though penalties and interest may begin to apply on July 1, 2020.
The City of Kitchener is waiving penalties and interest on property taxes for April, May, and June 2020. Late payment fees for payments due in April, May, and June 2020 for utilities will not be charged.
The City of Kitchener will also be launching an application-based property tax deferral program in June 2020. The City of Kitchener states that the program will allow residents and businesses to apply to extend 2020 final property tax bill due dates by 60 days.
The City of Mississauga deferred property tax due dates by 90 days to help ease the economic impact of COVID-19 on both residential and commercial properties. This pushed the April, May and June 2020 interim property tax due dates to July, August and September 2020.
The City of Mississauga deferred stormwater charges by 3 months. The Region of Peel is also allowing residents to delay paying their water bills between April 1 and June 30, 3030.
With changes occurring daily in response to COVID-19 it is vital that all property tax planning is done with the most up-to-date information. Gowling WLG is pleased to assist with any property tax appeals and deferral applications required during these trying times and recommend that these deadlines are scrutinized in an in depth manner.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.