Christopher Richards
PSL Principal Associate
Article
In a recent judgment, the Court of Appeal considered the proper construction of a clause that excluded liability for, among other things, "loss of profit, revenue [or] savings". The question (on which £80 million turned) was whether that clause also excluded a claim for wasted expenditure. We consider the impacts of the judgment in different sectors.
The case concerned a contract for the supply of an IT system. The system was delayed and, ultimately, not delivered. Towards the end of the contract, the supplier terminated the contract for the customer's non-payment of a £2.9 million invoice. The customer claimed that the invoice was disputed owing to the delays to the project, and so the supplier's termination for non-payment was a wrongful repudiation. The customer claimed damages of £132 million representing its wasted expenditure.
In a substantial first instance decision, O'Farrell J found that the supplier had wrongfully repudiated the contract, and that the customer had, in principle, established a claim for wasted expenditure. However, she also found that the customer's claim for wasted expenditure was entirely excluded by the exclusion clause in the contract.
The customer appealed the judge's findings on the construction of the exclusion clause.
The exclusion clause in question excluded liability for "indirect or consequential Losses, or for loss of profit, revenue, savings (including anticipated savings), data…, goodwill, reputation (in all cases whether direct or indirect), even if such Losses were foreseeable and notwithstanding that a party had been advised of the possibility that such Losses were in the contemplation of the other party or any third party".
The Court of Appeal held the judge was wrong to find this clause excluded the customer's wasted expenditure claim for five reasons:
For all the above reasons, the court concluded the judge's construction of the exclusion clause was erroneous, and the claim for wasted expenditure was not excluded.
The first instance decision in this case had caused some consternation for those involved in drafting exclusion clauses, as it left the claimant with limited remedy for wrongful repudiation. This Court of Appeal decision provides some welcome clarity and reiterates key principles of contractual construction enunciated by the Supreme Court in recent years:
Words matter - the court is primarily concerned with the natural and ordinary meaning of the words actually used by the parties. If the parties have used unambiguous language, the court must apply it.
Exclusions must be clear – if the parties intend to exclude liability for wasted expenditure (or anything else), then they should do so in clear terms. The more valuable the right being excluded, the clearer any exclusion clause needs to be.
Although the main issue in this case was the construction of the exclusion clause, there was also some interesting discussion of whether the supplier's unpaid invoice was properly disputed within the meaning of the contract (if not, then the supplier may not have wrongfully repudiated the contract). The court noted that the contract contained "pay now, argue later" provisions of the sort that underpin adjudications in the construction sector.
The Court of Appeal upheld the judge's findings that the invoice was formally disputed in good faith – there was no need for the customer to use the word "dispute", or to invoke a particular procedure; "we cannot accept this invoice for payment" was enough to register a dispute, and since the invoice was disputed, the supplier had not been entitled to terminate the contract for non-payment. Although it was academic because the court found the invoice was properly disputed, it also found that the "pay now, argue later" regime in the contract would have prevented the customer relying on set-off as an alternative reason for withholding payment, as that set-off had not been raised in the timeframes stipulated in the contract.
As O' Farrell J's two contrasting first instance decisions demonstrate, exclusion clauses of this sort are frequently at the centre of IT disputes. As the court recognised, wasted expenditure is arguably the paradigm claim when an IT implementation project runs into difficulty, so if the parties intend to exclude wasted expenditure, that needs to be made explicit.
As well as resulting in an important Court of Appeal judgment on exclusion clauses, the case is interesting more widely as it touches on topical issues in IT disputes including the use of agile implementation methodologies (on which there are still relatively few reported cases) and managing troubled IT projects.
If you have any questions about this article, please get in touch with Ashley or Helen.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.