In February 2018, we reported on the important judgment in Grove Developments Limited v S&T (UK) Limited [2018]. As set out in our review of the judgment, the judgment confirmed that a party does have the right to adjudicate on the "true" value of an interim application where there is either no Payment / Pay Less Notice or the relevant notice is deficient in some way.
As anticipated, the first instance judgment was appealed by the contractor, S&T, and the Court of Appeal judgment has been handed down today.
In February, Coulson J (as he then was) left a significant legacy in this, his last judgment in the Technology and Construction Court (TCC) before his elevation to the Court of Appeal. The judgment confirmed that a party does have the right to adjudicate on the "true" value of an interim application where there is either no Payment /Pay Less Notice, or the relevant notice is deficient in some way.
In reaching this judgment, Lord Justice Coulson (as he is now) finally turned the tide against the "smash and grab" adjudications that have peppered the construction industry for the last 20 years since the Housing Grants, Construction and Regeneration Act 1996 (now amended) (the Construction Act) first came into effect in 1998. He was clear in his intention in the Grove judgment stating: " [these] conclusions….. will reduce the number of 'smash and grab' claims which, in my view, have brought adjudication into a certain amount of disrepute".
This opinion is challenged in some quarters with the argument that the ability to claim effectively against a "crystallised" notice in such circumstances frees up the cash flow on a project, exactly as intended by the Construction Act.
The Court of Appeal judgment today has been much anticipated, and as expected, the appeal has been dismissed, leaving "smash and grab" adjudications in the dust, although interestingly, the Court of Appeal did not mention this phrase at all in their judgment, perhaps condoning the view that the phrase had unwarranted negative connotations.
The Court of Appeal upheld the first instance judgment, considering the six reasons why Grove was entitled to bring a separate adjudication to determine the correct value of interim application 22, even if (contrary to the judge's view) there was no valid Pay Less Notice. Those six reasons were:
This point is crucial for contractors to ensure cashflow, pending any later adjudication and adjustment. No great loss then in the departing "smash and grab" - pay now but adjudicate later is the message.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.