Vicky Fowler
Partner
Article
The UK Government has placed nine local planning authorities into “special measures” under section 62A of the Town and Country Planning Act 1990, allowing developers to bypass them and apply directly to the Planning Inspectorate. This article explains what this means in practice for major development schemes and how developers should respond.
From 15 June 2026, developers promoting qualifying schemes in those areas may choose to apply directly to the Planning Inspectorate (acting on behalf of the Secretary of State), rather than the relevant local authority.
This represents a notable intervention in the development management system and creates both opportunities and strategic considerations for housebuilders and commercial developers operating in these locations.
The following authorities have been designated:
The designations came into force on 15 June 2026 and will remain in place until the Government considers that performance has improved.
Designation is based on the Government’s assessment of an authority’s performance in determining major planning applications, focusing on both:
In this case, the Government concluded that each authority was "not adequately performing" its statutory function in relation to major development.
Section 62A designation (often referred to as “special measures”) does not remove the local authority from the process altogether, but it fundamentally changes the route to consent.
For qualifying major development (including schemes of 10+ homes, sites over 0.5 hectares, buildings exceeding 1,000 sqm, or sites over 1 hectare):
The decision has prompted strong responses from affected authorities, with some characterising the move as an erosion of local democratic control.
In particular, concerns have been raised that the designations rely on historic performance data and do not fully reflect more recent improvements. Some authorities are also considering options to challenge or seek reversal of their designation.
For developers facing slow or uncertain decision-making, the ability to apply directly to the Planning Inspectorate may provide a more predictable route, particularly where local refusal risk is high.
Designation introduces optionality, not obligation. Applicants must carefully weigh whether a Planning Inspectorate route is advantageous on a scheme-specific basis, including:
Applications submitted via section 62A are still determined against the development plan and material considerations, with input from the local authority. This is not a policy bypass, but a procedural alternative.
While the regime is designed to ensure effective handling of major schemes, developers should factor in the Planning Inspectorate’s existing workload and programme when considering this route.
The designations may result in an increase in section 62A applications, particularly in areas with constrained land supply (including Green Belt), where determination through the local authority has historically been more contentious.
For qualifying schemes, the section 62A route may be attractive where local decision-making has been slow or outcomes uncertain.
The decision to apply via the Planning Inspectorate or the local authority should be built into early project strategy, including programme and stakeholder planning.
Local authorities will continue to inform the decision-making process. Alignment with local policy and early engagement remain critical.
The Planning Inspectorate route brings different procedural considerations, which should be factored into delivery programmes.
Designations are not permanent and may be lifted if performance improves, particularly relevant for phased or long-term developments.
This is a clear signal of the Government’s willingness to intervene directly where it considers local planning performance is inhibiting delivery.
For developers, the introduction (or reintroduction) of a credible alternative decision-making route should be seen as a potentially valuable tool, but one that requires careful scheme-by-scheme assessment.
For more information, please contact our Planning team.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.
Gowling WLG est un cabinet juridique international constitué des membres de Gowling WLG International Limited, une société à responsabilité limitée par garanties enregistrée en Angleterre, ainsi que leurs affiliés respectifs. Les membres et affiliés constituent des entités autonomes et indépendantes. Gowling WLG International Limited promeut, facilite et coordonne les activités de ses membres, mais ne fournit pas elle-même de services aux clients. Pour en savoir davantage sur notre structure, consultez notre page Avis juridique.
© 2026 Gowling WLG Tous droits réservés