Smarter procurement and professional liability insurance
FPC/FJC :
JESSICA FOSTER: Good morning, everyone, or should I say the afternoon that we're going into. Welcome to session 3 of our second annual series, from bids to bricks. On behalf of myself, co-chair Jessica Foster from Gowling and Jerrie Lynn Morrison from Aon, who is filling in for our Aon co-chair, Kyle David.
Today, we want to extend a very warm welcome to you all joining us online. And truly a big thank you for making time in your busy schedules to be here. Again, I've said it before, but it bears repeating, your support and engagement are what make this series possible to now run in its second year, and we all truly appreciate it.
JERRIE LYNN MORRISON: Thanks, Jessica, and I echo those words and give a special shout out to the owners, contractors, designers, insurers, brokers, and of course, our fellow lawyers who make up the audience looks like we're at 30 right now and we're growing. So your collective expertise spans the entire construction cycle, making this series the perfect forum for candid dialogue about risks, rewards, and the realities of getting projects from concept to completion. If we could have the next slide, please. And Jessica will go through some housekeeping items.
JESSICA FOSTER: Yes, everyone's favorite. So very quick. Everyone's microphones are muted and cameras are turned off. This session is being recorded and it will be shared after the webinar. We will be allocating time for questions at the end of the session.
But if you think of something throughout, of course, feel free to send it through by clicking the Q&A icon at the bottom of your window, and we will address it in the time allotted. And we have one more housekeeping item on the next slide, which is, of course, our legal disclaimer. So we are not giving legal advice in this presentation. If you do have a specific question about your situation, Gowling WLG legal professionals would be pleased to discuss that with you.
JERRIE LYNN MORRISON: So today's session is titled build for success laying the foundation smarter procurement and professional liability insurance. Over the next hour and a half, we'll discuss procurement law basics, considerations, and pitfalls, as well as professional liability insurance as it relates to construction, including project, claims, and risk management considerations. We'd like to let you know that we are recording each session, so if you want to review anything you heard today, you'll find the recording and materials posted on the Gowlings event portal about a week after the session. Feel free to share the link with colleagues who couldn't be here today.
We'll be taking a break during the summer, and registration will open soon for the coming sessions that you see on the screen here in the fall. So please mark your calendars and join us for the remaining webinars. Also, a quick housekeeping note for the lawyers in the room. This program is accredited for up to 1.5 substantive CPD CLE hours. And I'll turn it over to Jessica again for a few more words.
JESSICA FOSTER: Thanks, Jerrie Lynn. So just to wrap it up, today's conversation, as always, doesn't need to end when the screen and the microphones turn off. If you have follow up questions or feedback on this session or the series as a whole, we would always love to hear that. I believe our contact information is somewhere in this deck. And certainly a quick Google will bring up mine.
We genuinely enjoy the dialogue in the learning that we've created here, and certainly we learn as much from you as you're learning from this series. On that note, you will all be receiving a feedback survey after this session.
Please, please take a moment to fill it out. It won't take long. Your feedback is so important to us to make sure that the content we're including in this series remains valuable and practical for you to use on the ground. With that, I'll hand it back to Jerrie Lynn.
JERRIE LYNN MORRISON: OK. If we can have the next slide, please. So thank you again, everybody for your time, attention, and enthusiasm. It gives me great pleasure to introduce Alexis Rivait, who will be our second speaker. So you'll hear from her a little bit later on.
Alexis is a senior vice president and national leader within our professional services group at Aon. She holds a fellow chartered insurance professional designation, as well as the certified risk manager designation, and her expertise includes public and private directors and officers, liability insurance, special placements such as IPOs and up listings, employment practices liability, fiduciary liability, and crime insurance. We look forward to hearing from Alexis after Christina, who will now be introduced by Jessica.
JESSICA FOSTER: Thanks. I have the pleasure of introducing Christina Kaminski. Christina is a senior associate based out of Gowlings Ottawa office, and she has a broad practice focused on corporate and commercial matters. But as well as procurement law, which she will be speaking about here today.
In Christina's procurement law practice, she's worked with both private and public sector entities across a wide range of industries and has a lot of experience drafting competitive solicitations and generally assisting clients at each stage in the procurement process. So very happy to have her with us today, and I will hand it over to Christina to kick us off and get started.
JERRIE LYNN MORRISON: Wonderful. Thank you, Jessica. Can everyone hear me? Perfect.
So just going through what we're going to be discussing today. So as was mentioned, my name is Christina Kaminski, and I'm a lawyer with Gowling. Our procurement team in the Ottawa office consists of myself, Graham Ragan, and Stephanie Pearce. And as Jessica mentioned, we work with and advise various public and private sector entities to help them navigate through the evolving procurement landscape, particularly with recent policy and regulatory developments at both the federal and provincial levels.
So today, I'll be presenting on various foundational procurement law principles and best practices, and going over some procurement drafting considerations and common pitfalls and problems. And then I'll pass it over to Alexis who will discuss the professional liability insurance. And we will then, if time permitting, move over to a Q&A portion.
Procurement law governs how public and in some cases, private organizations acquire goods, services, and construction work through competition. And we can think of it as a structured shopping experience with established rules that promote equal treatment of suppliers, accountability and spending, and compliance with legal obligations throughout the procurement lifecycle.
Now, the guiding principles of procurement are threefold. The first value for money, and this is a cornerstone of accountable government spending and provides assurances for taxpayers. And this is also done by removing barriers to trade and harnessing free market forces in controlled competitive environments. Second, overriding obligations of fairness, openness, and transparency. And these obligations begin once an owner decides to obtain goods and services and continues through to contract award.
And finally trade liberalization. Trade agreements allow for greater transparency and provide an even playing field for potential suppliers. Now, procurement processes are governed and informed by various instruments that work in harmony together. This includes the trade agreements, domestic legislation and regulations, bylaws, directives, policies, the common law, and as well as the respective rules and procedures that are set out in the solicitation documents, all of which lays the groundwork for how owners structure and develop their procurements. Next slide.
Now, procurements exists in both private and public levels. Public procurement involves an owner that is a public body or an organization that's required by legislation to observe the same rules and obligations as public bodies. Now, these public entities will be compelled or obligated to procure their goods or services in a structured procurement in accordance with specific statutory or other such obligations.
Now, private corporations can also engage in contracting through a procurement framework, and we've often seen this done when market availability or competition is unknown or even when private corporations are just looking to make more informed decisions. Now, while many of the same principles apply to procurement processes, regardless of whether the players are public or private, there also are some key differences.
Most notably, a private procurement is only governed by the common law and is not subject to any trade agreements or other statutory or legislative measures, which would typically govern how procurement is conducted at the public side. And this in turn impacts the remedies that are available. So in private procurement, there is no administrative tribunal or judicial review available to review the contract award decision or to find that a bidder is non-compliant. Typically, the focus is on damages. Next slide, please.
So in Canadian procurement law Contract A and Contract B is a unique legal framework that governs many competitive bidding processes. These concepts originated from a notable Supreme Court of Canada decision, referred to as the Ron Engineering and Construction case, and this has shaped procurement law across Canada. The basic idea is that when an owner issues a tender call and a bidder submits a compliant bid, two separate contracts will arise. The bidding contract, which is known as the Contract A and the actual construction supplier services contract for the work, which is known as Contract B.
So Contract A is formed when a compliant bid is submitted in response to a tender call. We can think of Contract A as the set of procedural obligations and legal obligations that regulate the competition itself, and implied duty of fairness is created when Contract A is formed. And this duty, which we'll speak about more later on in the presentation, is broadly defined, but it essentially obligates owners to treat bidders fairly and equally throughout the procurement process.
And notably Contract B, the performance contract, which will arise later when the owner accepts a successful bidders tender. And Contract B is the substantive agreement that governs the actual performance of the project.
Now this legal framework creates legal duties during the procurement process itself. So for example, an owner may be found liable if it accepts a non-compliant bid contrary to the tender documents, if it fails to follow mandatory evaluation criteria, or if it breaches an express or implied duty of fairness. Likewise, a bidder may be found liable if for instance, it withdraws an irrevocable bid or it refuses to execute Contract B after being awarded the work.
One thing we'd want to note is that not every procurement process creates a Contract A. This Contract A, Contract B analysis most commonly applies in formal tendering, which has strict bidding rules. But there are more flexible procurement methods such as request for proposals, request for prequalification, and the like. And these may be drafted specifically to avoid creating Contract A obligations.
We know that courts examine the wording and the surrounding circumstances of these solicitations to determine whether Contract A arises. So just including a provision that Contract A doesn't apply is generally not enough. There are some defining features of Contract A that have developed over time through the common law, and some of which are highlighted on the next slide.
So as was mentioned, some key features that have been defined over time through the common law include whether a bid is irrevocable or revocable, what the bid security requirements are, and how they bind or are applied to the bidder, whether there's disqualification provisions for non-compliance, whether post submission changes are permitted, whether Contract B has been attached, and whether there's an obligation to accept Contract B in the form that's attached just as well?
There's provisions on fixed and non-negotiable pricing, whether there's a requirement to sign proposal forms, whether there's constraints or parameters around negotiations, and of course, whether there's the use of traditional tendering terms, phrases, and concepts. So this is not a comprehensive or prescriptive list, but it does serve to outline some of the many key characteristics and considerations giving rise to a common law finding of Contract A.
So the courts have used the implied duty of fairness to extend legal obligations under Contract A. There is an implied term requiring that the procuring entity be fair and consistent in the assessment of all bids, and the duty of fairness does not arise until Contract A is formed by the submission of a compliant bid.
Now, some of these obligations of the duty of fairness are outlined on the slide. But there are two that we want to highlight in particular, one of which is the duty of disclosure. So an owner is under a legal duty to disclose all of the relevant and material information that may influence a bidder's decision to submit a bid or the price in their bid. So when developing solicitation materials as a best practice, information should be provided with the average bidder in mind and the such information should be correct, complete, and any material information should be included and any unreliable information should be left out.
Prior to tendering, owners have a duty to disclose in the documents the basis for which the bids are going to be evaluated and how the successful bidder is going to be selected. As well this includes the duty to disclose the relative weighting or the scoring of the various evaluation categories. It does not necessarily mean that you need to provide a breakdown to the microscopic detail of everything that's going to be considered in the evaluation, but it should be as transparent as possible.
The other duty we wish to highlight is with respect to compliance. Now, the law on this is clear in a formal bidding process and owners under a duty to reject non-compliant bids. If a tender is non-compliant, the bidders deemed to have failed the basic requirements and necessary for the owner to accept the Contract A offer, and now the benefit for the owner is that if a bidder submits a non-compliant bid and is rejected on that basis, the bidder cannot sue an owner for breach of contract, as there is no underlying contract formed in that case.
Now, we've talked a lot about tendering law and Contract A, Contract B, which structured firm and quite restrictive processes. And on the other side of the spectrum, we have negotiated RFPs. So a fully negotiable RFP request for proposal is a procurement process in which the buyer reserves the right to negotiate with one or more proponents after proposals are submitted, rather than being bound to award a contract based solely on the contract provided or the initial proposals.
So fully negotiated procurements typically feature a variety of elements. So for instance they're typically flexible with qualitative evaluations. They often avoid the concept of irrevocability.
They allow for post-submission, interaction, and discussion. They do not necessarily need to lock in pricing until an agreement is reached. And there's often a negotiation period or phase to finalize Contract B. And while these types of RFPs can reduce the rigidity and risks of classic tendering, they must still adhere to the principles of fairness and transparency, as well as any trade agreement obligations as applicable.
Now, the procurement documents must expressly allow for negotiations, so negotiation provisions in an RFP should not be ambiguous or unclear. It should be clearly set out how negotiations are going to take place, whether they're going to take place with one or more bidders, what the period for negotiation is, what the expectations are, and the like? And the more information that's provided, the more streamlined and efficient negotiations can be.
So in this table, we've set out some of the benefits and risks for negotiated RFPs and the classic Contract A, Contract B tenders. Ultimately, there's no one size fits all approach. Some procurement methods are better suited for certain projects. So for instance, where price is the sole consideration and the requirements are clearly defined, a classic tender provides reliability, it provides set terms, and it provides binding offers.
Comparatively, negotiate RFPs are often better suited for maybe mid to high complexity projects with less defined criteria, where innovation is often welcome and encouraged. And this enables both purchaser and vendor to collaborate. And as noted in the table, both options have their pros and cons.
One of the key pieces we flag to procuring entities with respect to whether they should incorporate negotiations into their RFPs, is whether this approach is effectively aligned with their current circumstances and goals. So the reason being that negotiations can go off the rails pretty quickly unless the procuring entity has dedicated resources to oversee and manage the negotiation process. In time sensitive projects, perhaps negotiated RFPs are not the best fit if it means allocating several weeks, if not months, to evaluate the submissions and then dedicate time to negotiate the agreement. Sometimes time constraints may lead bidders to strong arm procuring entities to settle for less desirable terms.
All this to say that these two procurement models are not the only options. There's also classic RFPs. There's vendor record arrangements, there's requests for standing offers, requests for quotations, et cetera. So it's advisable to consider if the goals and requirements for each project and to consider how best value will be achieved in those circumstances.
Maintaining if it ain't broke don't fix it. Mentality is not always suitable or advisable for each project.
So procurement drafting considerations. So in this section, we're going to be discussing some of the key provisions that we typically see in documents. So in any properly drafted solicitation we typically see parameters dealing with communication during a procurement process. And this goes back to fairness and ensuring that all bidders are treated equally and that they are provided with the same information.
So one of the things that are commonly found are addenda. So addenda are issued by the procuring entity and are used to modify or amend the procurement or the contract documents. Bidders should ensure that they have reviewed all addenda before issuing their submission.
With respect to meetings with bidders, we typically see this as held as information sessions or site visits, and these can either be optional or mandatory. From a drafting perspective, it's important to consider what the rules and intentions are of such meetings and riveters it's equally important to understand what the expectations are in terms of compliance? One case that we typically reference occurred where there was a mandatory site visit at a prescribed time. Being late was a grounds for disqualification.
One bidder showed up 15 minutes late, and unfortunately, that was a valid ground for disqualification based on the procurement documents. As well, post-bid clarifications, any clarification or communication post-bid should be carefully considered with respect to fairness for all bidders, and this includes considerations regarding issuing addenda post-submission deadline with respect to lobbying.
Now, lobbying and other activities intended by bidders to influence the outcome of tenders can threaten the integrity and outcome of the procurement. So for this reason, most RFPs contain prohibitions against lobbying, but procedural and organizational protections should also be put in place. And finally, there's also Q&A processes which I'll discuss in the next slide.
So where it is apparent that there's a lack of clarity or ambiguity with mandatory requirements. It is incumbent on a bidder to seek clarification or to object to the requirement, and Q&A processes have been integrated an integral part of most public procurements. So the terms around how it operates should be set out in the solicitation documents itself.
Typically, questions are submitted to the owner representative or through the bidding portal, and the owner will answer questions which should be provided to all bidders. If not, this could result in discriminatory treatment. The questions and answers should also get incorporated into the RFP as amendments. This will ensure that all bidders have the same information, as well as ensuring that the information will bind bidders when they respond with their bid.
The misuse of the question and answer process can lead to a procurement challenge. In terms of best practices, it's important for bidders to remember that if there is a defined process, it must be followed. This includes ensuring that questions are submitted on time if there is a deadline.
It's also advisable to avoid questions that are confidential or strategic, and there is a balance with the Q&A process. So considering balancing whether you should ask the question and maybe getting an answer you don't like or tipping your hand to other bidders versus not getting the information that you need. There's a bit of strategy from a bidding perspective that goes into it.
With respect to owners, it's important to respond to the question being asked rather than undertaking a grand analysis or presuming an underlying motive. And if a response, results in the issuance of addenda or results in effectively material amendments, it's advisable to extend a submission deadline to ensure that bidders can accurately respond to these changes. Next slide.
So moving on to evaluation criteria. So all evaluation criteria must be specifically set out in the solicitation documents and the relative weighting and importance, so their scoring and point allocation must be described. And if applicable, the solicitation must also indicate whether and under what conditions, alternatives or substitutes will be considered.
An evaluation or award is considered unreasonable if evaluators are found to have not evaluated a bid properly, whether they misinterpreted the scope of a solicitation requirement, if they overlooked important information, if they use undisclosed criteria, or they did not conduct the evaluation in a procedurally fair manner.
As a best practice, evaluators should not use undisclosed criteria. The marking grids given to evaluators should therefore align with the scoring described in the solicitation documents. The evaluation and the rules must be transparent and well-articulated in the RFP. And evaluators should must provide sufficient and reasonable reasons to support their scores, and this can often be done with scoring grids, but also through consensus. And the evaluation and scoring of proposals must be based on the requirements and the proposal in front of them, and not based on the scoring or comparison to other proposals.
So two other drafting considerations that we'll highlight is with respect to reserved rights and limitation of liability clauses. So reserved rights are often referred to as also privileged clauses or provisions that give the procuring entity a specific, reserved right, or privilege in the procurement process. Typically, the right to accept or reject a response in its discretion, or the right to waive minor defects, to cancel a procurement, to extend deadlines, seek clarification, et cetera. Typically, we often see these all set out in the same section under reserved rights heading.
The second clause that we typically see is limitation of liability or exclusion clause. Now, the leading case on the use of limitation of liability clauses is intercon, which is Supreme Court of Canada decision that set out a three part test to determine the enforceability of exclusion clauses. The first being does the exclusion clause apply to the circumstances. If so, was it unconscionable at the time the contract was made. And if not, should the court nevertheless refuse to enforce the exclusion clause because of an overriding public policy.
Now, since the court decision, there has not been a great deal of case law decisions that have been interpreted in the context of a limitation of liability clause in a tender process. But there are two cases one in Ontario, one in the Yukon, and the key takeaways are that a clear and valid exclusion clause will not be deemed void for overriding public policy unless the harm to the public is substantially incontestable.
So in the Yukon case, the court ended up finding that were the complainant was a sophisticated business party that is choosing to participate in a bidding process with an exclusion of liability clause. There was therefore no public policy interests that could justify depriving the government of the clause that the complainant had agreed to when bidding on the project.
So finally, I'll just be discussing some pitfalls and problems that we've come across in our practice. So first, being with respect to RFP documents post-closing, the submission deadline serves as an important reference point for the procurement process where we see issues arrive often is when the information or information is provided, accepted, or received. Post-closing and the solicitation documents do not contemplate how to address or deal with such issues.
So in general, the submission deadline is the line in the sand. Bidders must submit all required information and documentation before this deadline. Failure to do so is an automatic disqualification. To accept otherwise would introduce unfairness into the process in consideration that all other bidders respected and observed the prescribed timelines. In fact, unsuccessful bidders can challenge a process if after the bidding deadline, the owner seeks more favorable terms or grants a competing bidder with the opportunity to repair deficiencies in their bid.
For this reason, bidders cannot correct any material deficiencies in their bid post-closing. While there is a duty to treat all bidders fairly and not conduct what is known as bid repair, an owner is generally entitled to seek clarification and verify the information contained in a bid assuming that this is also prescribed in the solicitation documents. And to be clear, this would not be an opportunity for a bidder to add or change their pricing or improve their bid in any way. It's just confirming what has been presented in the bid submission.
Next thing we'll talk about is compliance. So a bidders conformance with mandatory requirements of a solicitation must be evaluated thoroughly and strictly. Mandatory requirements form part of the essential criteria and requirements of a solicitation and as we noted, Contract A would not be formed if the bidder is found to be non-compliant.
Now, the courts have noted that there is no such thing as a minor inconsequential breach of a mandatory requirement. However, if a proposal is not strictly compliant with rated requirements which are not mandatory, the aspect of non-compliance is merely a matter of form over substance, meaning that if they don't comply with technical criteria, this would be reflected in the point scoring. So they'd be given a lower score if they didn't address all of the requirements. Assuming again that this is on a non-mandatory basis versus mandatory requirements need to be complied with strictly.
In one case that we often cite to demonstrate how courts and tribunals have taken a strict approach when determining whether a bid is compliant is in one instance, the department of national defense sought to procure trunk lockers. And while the specifications specifically called for olive green handles on the lockers, the department awarded a contract to the bidder whose product had black handles.
Now, a competing bidder challenged the contract award, and the tribunal upheld that this bidder's complaint was valid because they viewed that the color of the handles was prescribed as a mandatory requirement, and the winning bidder should have been found non-compliant on this basis. And as a result, the tribunal awarded the complainant a portion of its lost profits and damages on account of the purchaser's acceptance of a non-compliant tender.
So the key takeaway from this case is that only those technical requirements and specifications that are truly essential should be listed as mandatory, since a purchaser is under a duty to reject tenders that fail to meet these mandatory criteria. And those standards, even when those standards may not be necessarily critical to the purchasers needs, so care must be taken in how things are worded, whether wording such as must or shall are incorporated, and what it means to be a mandatory requirement because it may compel the bidder can only award a contract to a compliant bidder.
In terms of best practice, compliance is a two-way street. Bidders are required to follow the process rules, but on the same site, owners are required to enforce them and are required to disqualify bidders who do not follow these rules. Failure to comply with mandatory requirements is in fact a ground for disqualification. However, a bid can contain simple omissions or irregularities and still remain capable of acceptance if it substantially complies with the RFP requirements.
Now, so as we've discussed, solicitation documents are really the roadmap and set out the rules of the game governing the procurement process. And in doing so, there needs to be in alignment with how the solicitation documents work and how they are read with the contract documents. Treating these two documents as standalone materials that do not speak to each other, it runs the risk of major inconsistencies that could impact the project.
In terms of best practices, we would note that it should be clearly stated what the roles and responsibilities are. And what we mean is that in some instances, we come across solicitation documents where the role of bidder and preferred bidder and contractor appear to be conflated or they overlap. So the solicitation packet should clearly distinguish between the requirements of the bidder under the RFP or tender and what they have to submit in their submission. The requirements of a preferred bidder as conditions precedence, for instance, to be awarded the contract, and finally the obligations of the successful contractor under the agreement.
Clarity benefits bidders and owners alike, so ensuring that roles and responsibilities are clear and comprehensive will help reduce any ambiguity. Second point we notice in terms of alignment of risk. This is closely tied to the previous point where a reoccurring problem is a misalignment between the procurement documents and the final contract. So ensuring that insurance, bonding, schedules, warranties, liquidated damages, and other key commercial terms match the contract be and are achievable when required. Avoiding shifting risk or adding material terms post-award that were not disclosed is recommended.
Another thing we'd flag is in terms of providing again, disclosure and providing sufficient information. And this includes background information. So disclosure of material site and project information such as site conditions, investigations, owner diligence is done in a balanced manner. And this will help clarify the standard of reliance without withholding known material risks.
If disclaimers are used, ensuring that they're reasonable and don't undermine fairness and the ability to price risk. But it should also understand what needs to be included in their bid response and what their obligations will be under the contract. Building on this, defining the scope of work should also be clearly set out, so ambiguity and scope can often lead to inconsistent bids and eventually downstream disputes. Providing clear technical requirements, performance standards, interfaces, deliverables, and identifying any assumptions and exclusions will help govern pricing and risk.
And finally, with respect to incorporating documents by reference and managing the contract, it's important and worth specifying which documents will be incorporated into Contract B into the contract, including the RFP or certain proposal extracts, and how and what order of precedence and how conflicts between these various materials will be resolved? Identifying which parts of the proposal are binding, such as technical key personnel pricing and avoiding unintentional incorporation of perhaps marketing material or other ambiguous commitments.
And ultimately, one thing that we always advise is to confirm if your procurement documents or bid documents are still working for you. In our experience, recycling old project documents and hoping that they still work is not always the best approach, particularly for owners it runs the risk of using outdated practices, misaligned procedural rules, and perhaps further issues down the line. It's always recommended to consult with legal counsel and subject matter experts to ensure that the criteria accurately reflects project requirements and that the instructions are clear and unambiguous, and that the rules are being applied fairly inconsistently. So with that, I'll pass it to my co-presenter, Alexis.
ALEXIS RIVAIT: So before we get to the discussion about the specific policies, I want to lay the foundation and make sure that everyone understands what the professional liability policies intend to cover. The coverage under a professional liability policy is for negligent acts, errors, or omissions of the insured professionals. Some policies can provide broader coverage. However, this is the basis for all policies.
The professional liability policy can cover legal fees, settlements, and judgments up to the policy limit. It's really important to understand the limitations of these policies in order to also understand the risks assume under contracts as well as uninsured exposures.
Who is a professional? Essentially, it's someone who possesses distinctive qualifications and conforms to the technical or ethical standards of a profession. It's having or showing great skill or competence, being an expert, and the mastery and use of a specialized body of knowledge.
Some policies will specify who is considered a professional. Some insurers require professionals to be licensed, others require a certain number of years of experience. It's important to vet the definition against your employees experience and qualifications, and to negotiate this definition with the insurer to ensure alignment of coverage.
What is professional negligence? It's when there is a duty owed and a duty breached. A failure to meet the standard of care expected of a similarly qualified professional in similar circumstances.
The standard of care represents a standard of performance which others have a right to expect from a professional. The common law standard of care for performance of professional services is generally seen as the ordinary and reasonable care usually exercised by someone in that profession on the same type of project at the same time, and in the same place under similar circumstances and conditions. Perfect performance is not required by common law.
What would a breach of the standard of care look like? Here's a hypothetical situation. A municipality engages an engineering team to design a bridge rehabilitation. The engineer fails to apply current load bearing standards and does not identify known structural deficiencies during the inspection.
The result is that the bridge requires early closure and costly remediation. The breach was the failure to exercise the level of skill and diligence expected of a reasonably competent engineer under current standards. Next slide, please.
The definition of professional services is one of the most important definitions of the policy. And it has to be reviewed in relation to the services provided on the project. The definition should be comprehensive, but on projects where additional consultants may be added, mid-term or scopes of work may change, this clause should be revisited for adequacy.
The definition of professional services varies by insurer wording. Sometimes it points back to the declarations page and the application, for example describing the insured as a design build contractor as more fully described in the application and attachments. That's why complete underwriting information matters. Next slide, please.
Let's take a moment and look at the difference between a commercial general liability, a CGL, policy versus a professional liability policy. A CGL policy is meant to protect a business against third-party claims for bodily injury and property damage arising out of operations, products, physical work or premises. It's oriented towards tangible harm.
Professional liability, by contrast, is often framed around financial damages arising from professional services such as advice, design, consultancy, and reports. As a hypothetical example, let's say you have a municipality who inspects and approves the installation of stormwater drainage system for a new residential development. Due to an error in the engineering review process, the system is undersized and does not meet required capacity standards.
Following a major rainfall event, the system fails, causing flooding damage to multiple homes. Homeowners file claims alleging property damage, and the municipality initially tenders the claim under its CGL, commercial general liability policy. The insurer denies coverage under the CGL policy, because the damages arise from a professional services error i.e. negligent design review and engineering oversight, and did not arise from an occurrence causing damage in the traditional CGL sense.
So now we're going to examine project specific professional liability. A dedicated project policy matters more as projects grow larger and more complex, where relying on the annual policies that consultants and contractors already carry becomes a real exposure. Consultants typically carry only two to $5 million in limits, and while contractors usually buy $5 million or more, some carrying no annual professional liability coverage at all. Those annual limits are shared across every project the firm works on, so a loss elsewhere can leave little behind for yours. And because limits are usually inclusive of defense costs, a drawn out claim can erode them quickly.
Contractual limitations of liability add to the risk, since architects and engineers without large fees often won't expose their full limits to a single contract. Capping their liability to fees or low insurance amounts. When contracted to multiple parties, a claim can mean pursuing several different insureds backed by several different insurers, which protracts the litigation and slows settlement. On sizing, project policies are normally arranged for projects over $50 million, while for smaller projects the annual policies should be adequate.
A project specific professional liability policy is bought for one project, either because the contract requires it or as a risk management practice, and it is best to have an organizational chart so all proper entities are named. Limits apply per claim and in the aggregate and include defense costs. So even when no indemnity is paid out, the cost to retain defense counsel and experts can be significant.
Coverage is typically limited to declared insureds only with no broad form, which is another reason the named entity organizational chart matters. It's written for the construction term plus an extended reporting period, an ERP. The time after the policy expires, typically at substantial completion, during which the insured can still report claims.
Because it is a claims made policy, claims must be reported during the policy period, or that extended reporting period and reporting obligations apply by policy section, so meeting them is critical to securing coverage. The retroactive date should be set to the date the first professional services were rendered. Oftentimes, the first date of design.
Total market capacity varies with project type, size, and duration, as well as the market's experience with the project participants. Expect these policies to be expensive. Premiums on mega and large civil projects are high because insurers anticipate full limit losses on primary layers, and project policies generally cost more given the number of claims paid out on them in the past.
So these are key exclusions to watch most closely. And the message here is to read them carefully when negotiating contracts, because the wording in the agreement can quietly widen or narrow what the policy will actually respond to. For the contractual liability exclusion, warranties, guarantees, and liquidated damages are excluded unless the professional would have been liable even without the agreement.
The policy is meant to cover what the professional is liable for at law i.e. the standard of care we discussed earlier. Phrases like the highest standards in the profession, or best professional standards or requirements to perform to the client satisfaction or free of defect, alter the standard of care and the assumed liability. Committing to a higher standard through that language not only increases exposure, it can create an uninsured exposure for the firm under this exclusion.
Watch indemnity sections that require defending the client regardless of negligence. Without a prior finding of negligence, there is no legal obligation to pay those defense costs, so the policy may not reimburse them. The insured versus insured and related entity exclusions strip out claims between parties on the same policy or between affiliated entities.
Faulty workmanship is excluded unless it arises out of professional services. Design or manufacture of goods or products is excluded, though there is typically a carve back for products designed specifically for the project, and some UK forms may exclude consequential losses, pollution, asbestos, and mold, and can also limit cladding and fire safety claims. Under the other insurance clause, the policy is primary except over the policies listed out where it sits excess, for example, over a wrap up in builder's risk.
So now we're going to look at single project professional liability. When we talk about professional liability on a project, there isn't a single right policy. There are several options, and each one is built to protect a different party.
First the A&E, architects and engineers, single project policy. This is a project specific professional liability policy that covers the design team, the architects and engineers, for this one project. It's the most familiar starting point and responds to errors and omissions in the design work itself.
Second on the list is the CPPI, the contractors protective professional indemnity. This protects the contractor for professional liability exposures they take on. For example, through design build or delegated design. It covers the contractor's interest rather than the designer's.
Third on the list is the CPPI wrap. This broadens the coverage to bring the contractor and the design team under one policy. The trade-off to flag here is the insured versus insured exclusion. Because both parties are insured under the same policy, claims one insured brings against another are typically excluded. That's an important limitation to understand before relying on a wrap.
And fourth on the list is the OPPI, the owner's protective professional indemnity. This policy covers the owner and gives them an additional layer of protection above the designers own coverage responding to these owner's interests directly.
These policies aren't mutually exclusive. On a single project, you can layer more than one of these policies together because each one protects a different interest. The key takeaway is that choosing the right structure is about matching coverage to whose risk, you're trying to protect. So let's review each type of policy in more detail.
For an architects and engineer policy, the named insurers typically the prime consultant plus sub-consultants or multi-prime plus subs. It typically requires reporting of new architects and engineers during the policy term. The policy types we discuss will differ as to who the named insured, along with the coverages provided. That said, all of the policies will share the third-party liability section, which responds if the insureds get sued for actual or alleged negligent acts, errors, or omissions.
The policy will defend the insureds and pay compensatory damages if the insureds are found to be negligent. There's also coverage for mitigation of loss, also known as rectification, which pays to mitigate, or rectify losses that would otherwise become a claim under the policy. The insurer typically needs to be notified and approve any actions prior to the mitigation of loss action taking place. It's extremely important to remember this, as many claims have been denied under this section for late reporting.
There's also a baseline changes endorsement, which outlines conditions which are considered material and which must be reported to the insurer for evaluation. This would include large increases in project values or fees, change of delivery model, change in project financing, and change in the scope of work. You would use this type of policy for any project size or delivery model other than a PURE Alliance or IPD.
North American insurers each typically deploy between $5 and $10 million in limits, with UK insurers generally deploying smaller limits as the layers of quota shared. Retentions are dependent upon the insurer as well as the project, and maximum policy terms may be limited to 10 years by some insurers, posing challenges for larger and longer projects.
The CPPI policy is designed to respond to design claims brought against design build contractors. Because third-parties can and do bring such claims, the contractor requires its own professional liability coverage. In practice, however, claims of this nature remain relatively infrequent. With respect to rectification or mitigation of loss, the key point to note is that the insurer typically requires pre-approval before any rectification or mitigation costs are incurred. Insurer consent should therefore be obtained before proceeding.
We also want to highlight protective indemnity. On design build projects, the more severe design claims are typically brought by the design build contractor against its own design subconsultants. This is precisely the exposure that the protective indemnity is intended to address.
In terms of what protective indemnity provides to the contractor, it operates as a first-party loss coverage. It indemnifies the contractor for its own losses, including delays and cost overruns. Where those losses arise from the negligence of a subcontracted professional, the coverage sits excess of or on a difference in conditions basis to the primary professional liability policies maintained by the architects, engineers, and other construction professionals. The policy stipulates a minimum insurance requirement that those parties are obligated to carry.
It is also important to understand when the CPPI drops down to respond. There are three circumstances where the design professionals limit has been eroded or exhausted through the payment of claims, where design professionals underlying professional liability limit has not been maintained, or where the CPPI terms and conditions are broader than those of the design professionals underlying policy.
Two procedural conditions are required by the insurer. The insurer must be notified at the same time the claim is made against the design professional, and the insurer must consent to any settlement. Both requirements should be observed.
To illustrate this, consider a design build project in which the surveyor makes an error and the piles are installed in the wrong location. The first response is to trigger rectification in order to correct the position of the piles. The second is to trigger the protective coverage in respect of the resulting delays and cost overruns. A single event therefore engages two distinct triggers, which is the central principle to this coverage.
You can use this policy for any project where the contractor is providing professional services, or is legally liable for subcontracted professional services, other than a PURE Alliance or Integrated Project Delivery, IPD. Ensures each typically deploy between 5 million and 10 million limits, and retentions are dependent on the insurer and vary between $100,000 up to $1 or $2 million, particularly on the rectification coverage. The maximum policy term may be limited to 10 years by some insurers, posing challenges for larger and longer projects.
This slide addresses the CPPI wrap, which brings the construction and design parties together under a single policy. The name insureds are the contractor entity together with all subcontractors, architects, engineers, consultants, and subconsultants providing professional services on the project. Because the policy covers both the contractor and the architects and engineers, the definition of professional services needs to be drawn broadly enough to capture the full range of activities undertaken by both groups. The policy response to three triggers financial loss, bodily injury, and property damage.
In terms of structure, this is a claims made and reported policy. Defense costs reduce the policy limits and deductibles which are paid by the responsible parties and can be significant. The defining feature of the wrap is the insured versus insured exclusion.
Because all parties sit under the same policy. The contractor is precluded from suing the other insureds, the architects, and engineers for delays and cost overruns. This is a principled trade-off of the rap structure. In practice, the implications of that exclusion vary. In many cases, the contractor may not wish to pursue the architects and engineers under the wrap, in which case the exclusion is of little concern.
Alternatively, the contractor may negotiate to retain the right to sue. Where that occurs, the architects and engineers annual policies are exposed or a separate single project policy may be arranged for them. It is also worth noting that some delivery models require only certain professionals to be insured under the policy on a PURE, IPD, or Alliance Project Policy, only the parties to the multi-party agreement being the owner, contractor, architect, engineers, and major subcontractors would be insured because the waiver of claims in that agreement precludes suits amongst those parties.
And finally, because the waiver of claims does not extend to professionals outside the IPD or Alliance agreement, those parties policies could still be pursued and protective indemnity would respond. Next slide, please.
A lot of the information on this slide is similar to what we've already seen with the other projects type policies, but I will call it a few exceptions. So as you can see, some contractors have in-house engineering arms whose engineers work closely with other subcontractor professionals on the project. In this case, the CPPI wrap is a good idea, as it may be difficult to prove whose negligence caused the loss.
And another distinguishing feature is that the retentions vary by procurement model. So for PURE IPD and alliance projects, the rectification retention is typically a portion of the risk pool, anywhere from 25% to 35%. The owner's protective professional indemnity policy, or OPPI, provides project owners with coverage for professional negligence claims arising from design or engineering services on a specific project. It acts as excess protection over contractors or designers professional liability policies, and includes defense costs if the owner is named in a lawsuit.
This coverage is critical for large, complex projects where owners face long tail risks and potential exposures to high severity claims. The professional liability coverage extends for the insurer to pay on behalf of the insured the amounts which the insured becomes legally obligated to pay because of a claim resulting from a negligent act or omission in a professional's activities and duties. There's the protective indemnity insuring agreement that's first-party cover, and this is where 90% of the claims are paid out. And this is the indemnity of the owner for loss incurred as a result of negligent professional services by or on behalf of the design professional.
The owner would have to sue the professionals, obtain a settlement and payment under the underlying policy prior to the OPPI responding, and the pursuit costs are not covered. The policy will provide primary coverage if the underlying limits are exhausted or the policy is not responsive. This slide sets out the owner's protective professional indemnity, or OPPI benefits.
In essence, it's the owner's own coverage. It ensures the owner's loss arising from the negligent design of the contracted design professionals. Importantly, it does not ensure the design professional and it provides defense and indemnity to the owner only.
The main benefit is consistency. A single policy gives the owner one consistent source of coverage. It responds where the design professionals own policy does not. For example, due to limit exhaustion, a lapse in cover, or an exclusion. In other words, it operates as a difference in conditions cover for the owner.
A few further advantages worth noting, the OPPI limits are not eroded by claims made against the design professionals. So the owner's protection stays intact. It also helps the owner manage limitation of liability demands, and it can be structured to cover either a single project or multiple projects on a rolling basis.
On cost, OPPI is significantly cheaper than a project A&E policy and somewhat cheaper than a CPPI depending on the underlying coverages. Part of that savings comes from reduced markup by the design professionals who keep their practice policy retention rather than being subject to the higher project policy retention. So OPPI can also be purchased excess over projects specific cover.
I'm going to spend now a few minutes talking about the state of the professional liability marketplace. What we're seeing most consistently is rate stability across the professional liability portfolio. There are a couple of reasons for that. First, loss experience has generally stayed within expected levels, so carriers have not had to make major pricing corrections. Second, new capacity is entering or in some cases, re-entering the Canadian market.
We've seen insurers add professional liability as a product line, and we've also seen some carriers come back into the project specific space. That added competition is important because it helps keep pricing disciplined and gives clients more options. Project business is a good example. Not that long ago, many Canadian carriers had very little appetite there. Today we are starting to see more interest and more available capacity, which is helping create modest rate improvements.
That said, favorable market conditions do not mean underwriting has become casual. Underwriting is still a disciplined process. Underwriters continue to look very closely at your industry experience, the strength of your professional team, your project profile, and of course, your claims history.
So while the market is more competitive, the quality of the underwriting submission is critical. On coverage terms, the market is also stable, and we are beginning to see more room to push for broader wording. As additional capacity becomes available, our negotiating position improves, and that gives us the ability to pursue enhancements that may not have been available a year or two ago. In other words, this is not just about price. It's also about using competition to improve overall program quality.
There has also been some consolidation activity in the broader insurance market, and naturally, clients ask whether that will affect E&L or professional liability capacity in Canada. At this stage, we have not seen a meaningful impact in this segment specifically, but it is something that we continue to monitor closely. From our perspective, the priority is to take advantage of today's competition in a thoughtful way. That means securing the right terms, presenting a strong underwriting narrative, and being especially proactive where there's claims, activity, or anything else that may draw attention.
The clients who tend to achieve the best outcomes are the ones who start early. Come to market with clear information and approach renewals strategically rather than transactionally. So if you have a renewal coming up, bringing forward updated revenue detail, project information and loss activity as early as possible gives us the best opportunity to test the incumbent market and explore alternatives where appropriate, and drive the strongest overall result. So we're going to speak next about claims and risk management considerations. And next slide, please.
So architects and engineers face unique professional liability exposures due to design coordination and construction phase services. The points outlined on this slide highlight practical steps to help reduce the frequency and severity of claims, and to support a more favorable insurance outcome over time. So we've separated out into three columns. The first one is before you start.
Risk is largely set at the outset through project selection and contract clarity. Taking on unfamiliar or complex projects without clearly defining scope, roles, and reliance on others is where many exposures are introduced. The second pillar is during design and delivery.
Most claims don't come from a single failure. They come from breakdowns in coordination, quality assurance and quality control and change management. Strong internal controls and clear accountability across disciplines are what prevent issues from materializing.
The third pillar is if issues do arise, how you respond can significantly impact both cost and coverage. Early recognition, proper documentation, and timely notification to insurers are critical to protecting your position and preserving insurance coverage. Ultimately, the common thread across all three pillars is clarity, clear scope, clear communication, and clear documentation. That's what consistently differentiates well-managed risks from claims.
So I'm just going to go over a couple of case study scenarios and then we'll wrap up the presentation. So on this first case study it's with respect to an engineering operation. A small structural engineering firm with six staff designed the framing for a new condo development. Two years after construction, significant cracks appear in the concrete slabs. The builder alleges the design didn't account for load properly.
No injuries or property damage occurred, but occupancy is delayed and the developer sues for lost revenue and redesign costs. This is a classic E&O claim. It's pure financial loss with no third-party property damage.
There are two main risk exposures. There's the design and specification error. Small firms may lack the depth of peer review that larger firms have. An error in structural design or material specification. In other words, miscalculated load capacity could lead to costly rectification costs, either during construction or after the project is completed.
The other risk exposure is project complexity and scope creep. Condo developments involve multiple professionals. Miscommunication or a lack of clarity and scope can result in disputes or the engineer being blamed for issues outside of their control. In addition, in large condo projects, engineers are frequently named in lawsuits regardless of whether their work contributed to the issue.
Plaintiffs often name all the design and construction parties in an effort to preserve rights and uncover liability during litigation. These claims can be costly to defend and may involve years of legal proceedings, even when the engineer ultimately bears no responsibility. Underwriters will want to see the contract with the developer, quality assurance procedures, and if a peer review was done, as well as past claims experience.
From a risk management consideration, you want to look at was there a clear scope of work. Were there any construction oversight roles and things to avoid are missing or vague contracts. Lack of documentation or re-engaging when there have been prior issues with the same developer.
This case study is with respect to a management consultant. So here we have a management consultant that's hired by a mid-sized manufacturing company to improve operational efficiency. They recommend restructuring departments and outsourcing certain functions. Six months later, the company sees a sharp decline in productivity and increased costs.
The client claims the consultant's recommendations were flawed and sues for lost profits and the cost of reversing the changes. This is a classic miscellaneous E&O loss. The client is alleging financial loss from poor advice. The main risk exposure here is professional negligence leading to financial loss.
The consultant made strategic recommendations that were implemented by the client and resulted in financial losses. The client alleged that the consultant failed to meet the standard of care as expected from a professional. Either through flawed advice, misrepresentation or insufficient analysis, this exposure is common in service based professions, where clients rely heavily on expert judgment and expect outcomes tied to financial performance or efficiency.
Risk management considerations include having clearly defined scope of services. Having copies of contracts or engagement letters, documentation of advice and client decisions, any disclaimers or limitation of liability clauses, and claims history and years of experience. The red flags would be if you had vague service scopes, no documentation, no contract. Big clients with high expectations or complex engagements handled by junior staff.
Those red flags aren't just warning signs, they're indicators of real exposure if not addressed through disciplined contract management and clear allocation of liability. From procurement to project delivery, clarity and contracts scope and liability allocation is what ultimately drives better outcomes. The right professional liability strategy ensures that when challenges arise, they don't become costly surprises. And this brings us to the end of our presentation. Any questions?
JERRIE LYNN MORRISON: Do you mind if I ask a question? So my question's for Alexis. Could you go over again, I know you had talked about the difference between professional liability and CGL.
So I'm thinking specifically about the, I forgot the acronym, OPPI owners. If you could go through maybe a scenario where that would respond in case anyone's thinking that a different policy might respond. Why would it be better to have that coverage?
ALEXIS RIVAIT: Sure yeah. It's really just designed to protect the owner. So the limits themselves can't be eroded by anyone else. It's almost like an extra layer of insurance.
So when you're underlying other designers policies, their limits are eroded and there's no coverage left there for you to make yourself whole from a loss. Then you can rely on that OPPI policy to fill the gaps of any of that uninsured remaining loss, because there's no more limit left to cover those.
JERRIE LYNN MORRISON: So again, we'd like to thank everyone for your attention and attendance. And if you do have any questions afterwards for either Christina or Alexis with regards to procurement or with regards to professional liability, please don't hesitate to reach out to any of us here at Aon or Gowling.
JESSICA FOSTER: Great. Thank you again everyone.
Join Gowling WLG and Aon for the next installment of our seven-part webinar series designed to help construction and infrastructure stakeholders navigate an increasingly complex project landscape. Whether you are an owner, contractor, consultant, or insurance or risk management professional, this session will provide practical insights to support informed decision-making throughout the project lifecycle.
We will focus on procurement strategies and professional liability insurance, with a focus on key legal principles and risk management considerations.
Procurement topics include:
Professional liability insurance topics include:
This program is eligible for up to 1.5 hours of substantive CPD credits with the LSO, the LSBC and the Barreau du Québec.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.
Gowling WLG est un cabinet juridique international constitué des membres de Gowling WLG International Limited, une société à responsabilité limitée par garanties enregistrée en Angleterre, ainsi que leurs affiliés respectifs. Les membres et affiliés constituent des entités autonomes et indépendantes. Gowling WLG International Limited promeut, facilite et coordonne les activités de ses membres, mais ne fournit pas elle-même de services aux clients. Pour en savoir davantage sur notre structure, consultez notre page Avis juridique.
© 2026 Gowling WLG Tous droits réservés