Sue Ryan
Partner
Article
9
In this latest 'Adjudication Watch' our construction team reviews key cases relating to adjudication from the last few months.
The background to this Technology and Construction Court (TCC) decision is that Cumberland engaged AMD to carry out mechanical and electrical sub-contract works at the Hilton Hotel on Park Lane in London. In March 2015, AMD claimed a final account sum of £527,770.33. Cumberland did not agree with the amount claimed and after several months of correspondence about the claim, AMD issued a notice of adjudication on 2 September 2015.
AMD was largely successful in its claim - the adjudicator determined the value of the sub-contract works was £464,448.34 and that Cumberland was required to make payment to AMD for the outstanding balance plus interest. As these sums were not then paid by Cumberland, AMD applied to the TCC for enforcement of the adjudicator's decision.
In the TCC, Cumberland argued that the dispute had not "crystallised" before the adjudication notice was issued and raised a further jurisdictional point contending that the adjudicator had failed in his decision to address certain important matters.
The TCC gave Cumberland's arguments short shrift describing both challenges as "hopeless".
On crystallisation of the dispute:
On the alleged failure by the adjudicator to address certain matters in issue:
TCC's decision - in addition to enforcement of the adjudicator's award:
The decision highlights the need to consider the weaknesses of any defence to adjudication enforcement and, if possible, take an early view on prospects and settlement. Otherwise, you risk being ordered to pay a high rate of interest and indemnity costs.
This dispute largely related to the interpretation of paragraph 8(1) of the Scheme for Construction Contracts 1998 (as amended) which states:
The adjudicator may, with the consent of all the parties to those disputes, adjudicate at the same time on more than one dispute under the same contract.
On 7 March 2014, Beck (as the main refurbishment contractor) engaged DATL as a sub-contractor to supply and install joinery items in the Lanesborough Hotel at Hyde Park Corner, London. Disagreements arose and various adjudications followed, all involving the same adjudicator:
Shortly after DATL commenced Adjudication 3, Beck objected to the adjudicator dealing with two disputes at the same time and as a result, did not pay the sums awarded in Adjudications 2 and 3.
In enforcement proceedings, the TCC enforced the decision resulting from Adjudication 2 but not Adjudication 3.
Where the Scheme for Construction Contracts applies, this case serves as an important reminder of the need to obtain the consent of all parties if commencing two adjudications at the same time or a single adjudication covering two separate disputes - otherwise you risk significant wasted costs.
RMC was engaged as ground works sub-contractor by UKC for a housing project in Bedfordshire. On 6 May 2015, RMC submitted an application for payment claiming £248,053. No pay less or other notice was served by UKC (to challenge the application) and RMC claimed it was therefore entitled to payment.
After "four or five months of fruitless negotiation", RMC commenced adjudication and on 18 November 2015, the adjudicator ordered UKC to pay the sum claimed, together with further sums by way of costs and interest. UKC refused to pay and enforcement proceedings followed.
In short, RMC won and UKC failed to obtain a stay of enforcement. Notably, in the adjudication, UKC had disclosed some e-mails between the parties during negotiations over the disputed application despite RMC's contention that those e-mails were "without prejudice". UKC argued that no dispute had existed at the time of the adjudication as RMC had in some way withdrawn the application during the negotiations. The TCC held that on the facts, RMC had not withdrawn the application and that in any event, the correspondence relied on by UKC was privileged and should not have been disclosed to the adjudicator.
On the question of staying the enforcement, UKC sought to rely on the decision in Galliford Try v Estura [2015] arguing that to enforce the adjudicator's decision would result in "manifest injustice". Mr Justice Edwards-Stuart (who was also the Judge in Galliford Try) referred to paragraph 21 of his judgment in Galliford Try:
I should make it very clear that I regard the facts of this case as being exceptional, and those in the industry should take note that the course that I propose to adopt in this case will be appropriate only in rare cases.
He went on to confirm that the dispute now before him was certainly not one of those "rare cases" that would necessitate a stay of enforcement.
It is clear that the TCC has used this opportunity to make it clear once more that the court will seek to give effect to the intent of the payment and adjudication provisions of the Housing Grants, Construction and Regeneration Act 1996 (as amended) and the Scheme for Construction Contracts - that intent was to maintain cashflow.
So, protect your position by knowing and operating the payment provisions in your contract and ensuring you comply with the notice requirements - by doing this, you reduce your exposure to "smash and grab" adjudications resulting in decisions that are hard to challenge.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.