Emma Knight
PSL Principal Associate
Article
12
In Ravestein B.V. v Trant Engineering Limited [2023], the Technology and Construction Court (TCC) has refused a claimant's permission to appeal an arbitrator's decision under the Arbitration Act 1996 (Arbitration Act). In doing so, the TCC has issued further guidance on an issue that has been considered by the courts in a line of recent case law (which we discuss further below): namely, the requirements for a valid notice of dissatisfaction, under the New Engineering Contract (NEC) suite of contracts, with an adjudicator's decision.
Under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act), adjudicator's decisions are 'interim-binding', i.e. binding until finally determined by litigation, arbitration or by agreement.
Most standard forms of contract require the losing party in an adjudication to issue a notification (referred to as a 'notice of dissatisfaction' in the NEC suite of contracts) to the other party that it is dissatisfied with the decision within a set time frame. If it fails to issue a notice on time, and importantly, in compliance with any contractual requirements for such notice, then the adjudicator's decision will become final and binding and any further right to challenge enforcement of that decision will be lost.
Ravestein sought leave to appeal under section 69(3)(c)(i) of the Arbitration Act, arguing that the arbitrator's decision was "obviously wrong" on two counts since the arbitrator had both:
Alternatively, Ravestein submitted that the question was one of public importance given the widespread use of the NEC3 standard form (section 69(3)(c)(ii)).
Trant sought to uphold the arbitrator's award, contending that the decision was not "obviously wrong" since the arbitrator had correctly interpreted both the relevant notice provisions; and Ravestein's purported notice of dissatisfaction as solely disputing the jurisdiction of the arbitrator, and not identifying any dispute with the underlying merits of the decision.
In relation to the requirements for a valid notice of dissatisfaction, both Parties relied upon the earlier TCC" decision in Transport for Greater Manchester v Kier Construction Ltd [2021] EWHC 804 (TCC), in which the TCC had also considered the requirements for a valid notice of dissatisfaction under Option W2 of the NEC form. However, the Parties sought a different interpretation of that decision.
Ravestein argued that Transport for Greater Manchester confirmed that:
Trant argued that Ravestein's argument was based on an erroneous interpretation of Transport for Greater Manchester. In Trant's submission, the correct test laid down by O'Farrell J in that case was that:
The TCC upheld the arbitrator's decision and rejected the Claimant's application to appeal.
Her Honour Judge Kelly agreed with the Defendants that the correct interpretation of the earlier TCC decision in Transport for Greater Manchester was that the notice was required to identify both the matter disputed and the intention to refer the matter to arbitration.
She noted that O'Farrell J had "made it clear in her judgment that she was considering the two separate requirements contained within clause W2.4(2)". Namely:
The TCC held that it had not - also upholding the arbitrator's decision in this regard.
The email in question was sent by Mr. Ravestein to the adjudicator shortly after he rendered his decision, with Trant in copy, and stated that:
"After seven days you weren't entitled to make any rulings. You must also follow the rules of the UK in 1996 by the Housing Grants, Construction and Regeneration Act (Construction Act).
If you do not withdraw your ruling before tomorrow, our solicitor mister Hugh Smit will file request at ICE to reverse the ruling."
The TCC agreed with the arbitrator that Ravestein's complaint was clearly as to jurisdiction and made no mention of any challenge / complaint as to the underlying merits of the adjudicator's decision.
A further relevant factor which the arbitrator considered would "militate against the email being a notice of dissatisfaction" - and with which the TCC agreed - was that Ravestein had sent its email to the adjudicator rather than to the other party as required by the clause (although it noted that the other party was copied in to the email).
Ravestein is the latest in a line of recent case law considering the requirements for validity of notices of dissatisfaction to be given by the losing party in an adjudication.
In Prater Limited v John Sisk & Son (Holdings) Limited [2021], the TCC confirmed that Clause W2.4(2) is concerned with circumstances in which a party is dissatisfied with the decision regardless of the grounds for that dissatisfaction. A notice of dissatisfaction will therefore be required both for challenges on jurisdictional or natural justice grounds, as well as challenges to the merits of the decision.
It is also worth recalling the TCC's further clarification in Prater that, for a party wishing to challenge the enforceability of an adjudicator's decision, it is not enough simply to challenge that decision in a notice of dissatisfaction, it must also "bring and make good that challenge before the Court".
Most recently, in Metropolitan Borough Council of Sefton v Allenbuild Limited [2022], the TCC held that whilst a notice of dissatisfaction "need not descend into the details of any substantive challenge to an adjudicator's decision" (per Transport for Greater Manchester), it did need to make it clear whether a challenge is being made to the validity of an adjudicator's decision on jurisdictional grounds, instead of, or in addition to, a challenge to its substantive merits. This decision was not cited by the TCC in Ravestein in which the requirement to identify the "matter disputed" appears to have been considered to require a challenge to the substantive merits only, since Ravestein's complaint about jurisdiction was not found to constitute a valid notice of dissatisfaction. It will be interesting to see if and how the two decisions can be reconciled if this issue comes before the courts again.
Following Ravestein v Trant, the position on notices of dissatisfaction appears - for now at least - to be settled: a notice of dissatisfaction under the NEC suite of contracts must identify both the matter disputed (i.e. the substantive merits and not just the jurisdictional challenge) and the intention to refer the matter to arbitration. If these requirements are not met there is a risk that a party attempting to notify its dissatisfaction with an adjudicator's decision will find itself with no further avenue to resist enforcement.
For Ravestein, failure to issue a valid notice of dissatisfaction resulted in the adjudicator's decision becoming final and binding and all further opportunity to challenge it being lost.
If you have any questions about this article, please get in touch with partner Ashley Pigott.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.