Bevin Shores
Partner
Article
8
The Ontario Divisional Court has found that procedural fairness constitutes a valid reason for judicial review of a determination of an adjudicator under Ontario’s Construction Act.
Interim adjudication remains an evolving area of case law; particularly concerning judicial review. In 2023, the profession took note of the Divisional Court's decision in Anatolia Tile & Stone Inc. v. Flow-Rite Inc.,[1] which, among other things, clarified the test for leave when seeking judicial review of an interim adjudication award.
Now in 2024, the Divisional Court has considered the question of procedural fairness as a ground for judicial review in Ledore Investments v. Dixin Construction.[2]
Judicial review of an interim adjudicator's determination is only available in the limited circumstances set out in section 13.18(5) of the Construction Act.[3] Fairness to the parties is addressed in paragraph 5, which provides that an interim adjudication decision may be set aside where "the procedures followed in the adjudication did not accord with the procedures to which the adjudication was subject under this Part, and the failure to accord prejudiced the applicant's right to a fair adjudication."[4]
In the adjudication decision under review in Ledore Investments, the adjudicator's determination turned on a point neither party had raised nor made submissions on. The dispute before the adjudicator had concerned, materially, three invoices for which the subcontractor sought payment from the contractor.[5] The contractor had been paid by the project owner, who was not a party to the proceedings. The contractor argued it was entitled to withhold payment to the subcontractor as set-off for deficiencies and delays. The subcontractor alleged that the contractor had not delivered a notice of non-payment within the time required under section 6.5(4) of the Construction Act, and thus was obligated to pay the invoices under the prompt payment scheme.
The adjudicator concluded that the contractor's failure to deliver notice of non-payment would have precluded them from relying on set-off, except that the contractor had not delivered a "proper invoice"[6] to the owner. This lack of "proper invoice" – even though it was the contractor's omission and not the subcontractor's – meant that the prompt payment provisions were not engaged, and the failure to give notice of non-payment was not fatal to the contractor's set-off argument.
The "proper invoice" issue was not raised by either party in the adjudication. This was acknowledged by the adjudicator, who commented that if the issue had been known or realized by the subcontractor prior to issuing the Notice of Adjudication, "perhaps the adjudication could have been structured in a way to deal with [the contractor]'s failure in this regard."[7]
The subcontractor sought judicial review, arguing, among other things, that there was a breach of procedural fairness. The Divisional Court allowed the application, concluding that there had been a breach of procedural fairness; and remitted the matter back to the adjudicator.
The key points from the Court's reasons include:
For the parties involved in adjudications, this decision underscores the need to balance the "fast and informal"[12] interim adjudication process with the reality that procedural protections inevitably involve some degree of formality and expenditure of time.
Familiarity with the process and being able to determine where efficiencies can be realized without unduly compromising fairness will be key to ensuring interim adjudication remains a useful tool for parties to deal with disputes.
[1] 2023 ONSC 1291 (Div Ct) [Anatolia Tile].
[2] 2024 ONSC 598 (Div Ct) [Ledore].
[3] RSO 1990, c C.30 [Construction Act].
[4] Although the applicant had also argued paragraph 13.18(5)(3) ("[t]he determination was of a … matter entirely unrelated to the subject of the adjudication"), the Court concluded they did not need to consider this provision in light of their finding on paragraph 13.18(5)(5).
[5] As noted in the decision at paragraph 7, additional relief had been sought before the adjudicator; however the focus of the judicial review application was three unpaid invoices and attendant holdbacks.
[6] Defined in section 6.1 of the Construction Act.
[7] Ledore at para. 20.
[8] Ledore at para. 25.
[9] Ledore at para. 28.
[10] Ledore at para. 36
[11] Ledore at para. 42, citing Thales DIS Canada Inc. v. Ontario (Transportation), 2023 ONCA 866, at para. 102.
[12] Anatolia Tile at para. 3.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.