Sean Garbutt
Principal Associate
Article
Nearly 30 years on from the Housing Grants, Construction and Regeneration Act 1996 (as amended) (the "1996 Act"), the Technology and Construction Court (TCC) continues to face questions concerning the validity, or otherwise, of Payment Notices and Pay Less Notices. In two recent judgments, the TCC has revisited, and reiterated, the core requirements for valid Payment Notices and Pay Less Notices under the 1996 Act and standard form contracts.
Two recent decisions - Vision Construct Ltd v Gypcraft Drylining Contractors Ltd [2025] EWHC 2707 (TCC) (Vision) and RBH Building Contractors Ltd v Ashley James & Anor [2025] EWHC 2005 (TCC) (RBH) - provide timely reminders on substance, form and timing, and the consequences of getting these wrong. For both payers and payees, the message is clear: strict compliance with the contractual and statutory payment regime remains essential, but the courts will apply a common-sense approach when interpreting notices.
In Vision, the court dismissed a Part 8 application brought by the payer, Vision Construct Ltd (VCL).
VCL had challenged an adjudicator's decision that it had failed to serve either a valid Payment Notice or Pay Less Notice in time, and that the contractor, Gypcraft’s interim application had therefore crystallised into the notified sum.
Three points from the decision are particularly important:
The practical message is clear: an untimely notice cannot be salvaged by re-labelling it.
Parties intending to serve both payment and Pay Less Notices must do so expressly, ensuring each document independently satisfies the statute and contract.
In RBH – which is a rare example of the residential occupier exception in section 106 of the 1996 Act being successfully used to challenge the enforcement of an adjudicator's decision - the TCC also considered the content requirements for Payment Notices and Pay Less Notices.
Two aspects are noteworthy for day-to-day administration.
The emphasis is on substance rather than style. The key question is whether a reasonable recipient, with knowledge of the contractual context and previous applications, would understand the sum assessed and how it has been derived.
You cannot retrospectively recharacterise a late or invalid Payment Notice as a Pay Less Notice: each notice must be timely, and "has to make plain that it is … a Payment Notice or a Pay Less Notice". Where both notices may be required in the same cycle, they should be drafted and served as distinct documents and must each meet its own statutory (and contractual) criteria.
The content test is pragmatic: payers should ensure that any notice discloses enough information for a reasonable recipient to understand the assessed sum and its basis; however, it does not require a full arithmetical breakdown.
Payment schedules and agreed timetables will be enforced according to their commercial intent: minor variations in terminology will not defeat an otherwise workable regime.
From an administrative perspective, both parties should:
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.
Gowling WLG is an international law firm comprising the members of Gowling WLG International Limited, an English Company Limited by Guarantee, and their respective affiliates. Each member and affiliate is an autonomous and independent entity. Gowling WLG International Limited promotes, facilitates and co-ordinates the activities of its members but does not itself provide services to clients. Our structure is explained in more detail on our Legal Information page.
© 2026 Gowling WLG All rights reserved.