Last month, Ofgem made its decision on the main package of connections reforms known as TM04+.
As part of these reforms, in-scope projects must provide evidence that they meet the new Readiness Criteria by making a readiness declaration with supporting evidence. This includes distribution-connected generation and storage projects above the TIA threshold.
National Energy System Operator (NESO) has now published an Evidence Submission Handbook designed to support project developers with the evidence required to support a readiness declaration. The Energy Networks Association has also published guidance on evidence submission on its website. This includes specific details relating to each Distribution Network Operator (DNO).
DNOs began accepting readiness declarations and evidence submissions earlier this week. If you are developing a relevant project and you have not heard from your DNOs, you should contact them now.
For further information on the connection reform programme, contact Gus Wood, James Stanier or George Nixon from our Energy team.
CECI NE CONSTITUE PAS UN AVIS JURIDIQUE. L'information qui est présentée dans le site Web sous quelque forme que ce soit est fournie à titre informatif uniquement. Elle ne constitue pas un avis juridique et ne devrait pas être interprétée comme tel. Aucun utilisateur ne devrait prendre ou négliger de prendre des décisions en se fiant uniquement à ces renseignements, ni ignorer les conseils juridiques d'un professionnel ou tarder à consulter un professionnel sur la base de ce qu'il a lu dans ce site Web. Les professionnels de Gowling WLG seront heureux de discuter avec l'utilisateur des différentes options possibles concernant certaines questions juridiques précises.