Gus Wood
Partner
Co-leader of Energy (UK)
Article
Ofgem has today approved the electricity licence and code changes needed to implement the transmission connection reform programme in Great Britain. The decision marks an important milestone for the programme, which will now move into the implementation phase.
TMO4 refers to Target Model Option 4 which was one of the options for reform proposed by the National Energy System Operator (NESO) and selected by Ofgem in December 2023. This was subsequently upgraded to TMO4+ when it became apparent that the initial reform would not be sufficient to deliver the reforms needed.
The general principle of the reforms is to move away from an approach of 'first come, first served' towards an approach of 'first ready and needed, first connected' - prioritising connections based on their readiness and on strategic alignment.
The newly introduced connections methodology introduces Readiness Criteria and Strategic Alignment Criteria. These criteria will be applied to the existing connection queue this year (Gate 2 to Whole Queue process), and then as standard going forward. The methodology applies to all transmission connections and to generation projects connecting to a distribution network which meet the threshold for a transmission impact assessment (TIA).
Readiness Criteria (in high-level terms):
Strategic Alignment Criteria (in high-level terms):
Designated by NESO - via project designation methodology.
Further detail on the reform package is set out in our January article.
The key change as compared to NESO's proposals is that the protection is now available to projects contracted to connect before the end of 2027 - whereas this was previously 2026.
The licence and code changes approved by Ofgem are now subject to a standstill period to allow for challenge.
The Gate 2 to Whole Queue process will then commence in May. All projects holding accepted transmission offers - and distributed generation projects above the TIA threshold - will need to submit evidence that they meet the new criteria. Having assessed eligibility, NESO will then issue revised offers based on the reformed queue. These are expected in the Autumn for projects connecting before the end of 2027.
There are also still further (secondary) code changes on which Ofgem's decision is awaited:
For further information on the connection reform programme, contact Gus Wood, James Stanier or George Nixon from our Energy team.
NOT LEGAL ADVICE. Information made available on this website in any form is for information purposes only. It is not, and should not be taken as, legal advice. You should not rely on, or take or fail to take any action based upon this information. Never disregard professional legal advice or delay in seeking legal advice because of something you have read on this website. Gowling WLG professionals will be pleased to discuss resolutions to specific legal concerns you may have.